Questions # 1:

Raincoat Incorporated is running a project with two major activities. Activity 1 will start on the 1st January and finish on the 1st June. Activity 2 will start just before the completion of Activity 1, around 15th May, and run until 31st December. What type of sequencing is being used?

Options:

A.

finish to start with lag

B.

finish to start with lead

C.

start to finish with lag

D.

start to finish with lead

Questions # 2:

In Project Management, what roles does theBoard/Steering Groupperform?Select TWO

Options:

A.

authorises the initiation of the project

B.

approves a budget to the project

C.

approves major deviations from the original plan

D.

replaces ineffective team members within the project group

Questions # 3:

What is aTheory-Driven Evaluation?

Options:

A.

an evaluation of the motives behind the project

B.

an evaluation which looks at “lessons learned” from the project

C.

an evaluation which provides quantifiable outcomes as to the success of a project

D.

an evaluation which examines how and why a project succeeded/failed

Questions # 4:

Derek is a Project Manager at Dandelion Ltd and is beginning the project initiation phase of a new project looking into the creation of a new product line. He is creating a business case for senior leadership. Should Derek include within this risks and concerns he has about the potential failure of the project?

Options:

A.

yes – it is important that senior management are aware of the risks and a contingency plan is included

B.

yes – all projects have financial risks associated with them and senior management must be aware of this

C.

no – the project initiation should focus on the value-add objectives of the project

D.

no – the project initiation focuses on the “why” of the project and should present a business case for completing the project

Questions # 5:

Lucy has just been told about a change at her company that will affect the way she conducts her job. She is currently feeling sceptical about whether this change is a good idea. According to theChange Cycle, which of the following stages will Lucy experience next?

Options:

A.

denial

B.

depression

C.

discomfort

D.

discovery

Questions # 6:

Zoe is a Manager at Friends Incorporated. The company is undergoing a major change to working practices, and Zoe has noticed that several of her team seem cynical about the changes. What should Zoe do?Select TWO

Options:

A.

cynical employees are a problem so should be dealt with via the disciplinary route

B.

highlight key achievements of the company and areas where the change has been successful

C.

allow for upwards communication and for staff to ask any questions

D.

there is nothing Zoe can do as the Psychological Contract is under strain

Questions # 7:

A large unpredicted event has occurred in the external environment which has affected Company X. Which of the following change responses would be most appropriate to this situation?

Options:

A.

incremental–reactive change

B.

incremental–proactive change

C.

proactive–transformational change

D.

reactive–transformational change

Questions # 8:

Freeman defines six stakeholder categories who are able to influence the success of a project.Select THREE

Options:

A.

owners

B.

creditors

C.

suppliers

D.

managers

E.

government

Questions # 9:

Bob is the CEO of a fast-growing electronics company. Bob has a high risk appetite and this is reflected within the company culture. Which of the following would be the best approach to manage risk at this company?

Options:

A.

tolerate all risks

B.

hire a project manager with a low appetite for risk to balance out the risk appetite

C.

set risk thresholds

D.

base the company’s competitive strategy on the risk appetite

Questions # 10:

Cleo is a Project Manager and is drafting a set of objectives for her project. She has decided that the project must have completed stages 1 and 2before the end of the financial year. This is an example of what type of objective?

Options:

A.

achievable

B.

relevant

C.

specific

D.

time-bound

Viewing page 1 out of 3 pages