Questions # 1:

What will happen in the MRP run if you have created a new MRP-relevant material that

supports both in-house production and external procurement?

Options:

A.

The MRP run assumes external procurement.

B.

The MRP run assumes in-house production.

C.

The MRP run does NOT consider the material; it has to be planned interactivelty

D.

The MRP run plans the material only if a quotation has been maintained.

Questions # 2:

Which materials have a negative quantity in a bill of material or in a recipe?

Note: There are 3 correct answers to this question

Options:

A.

Continuous flow materials

B.

Bulk materials

C.

By-products

D.

Co-products

E.

Waste products

Questions # 3:

Which master data fields can have an impact on whether MRP creates planned orders or purchase

requisitions for a material?

Note: There are 2 Correct answers to this question?

Options:

A.

MRP Groups

B.

Material Type

C.

MRP type

D.

Procurement Type

Questions # 4:

How can you characterize dependent requirements in material requirements planning?

Note: There are 2 correct answers to this question.

Options:

A.

They are created with exact times in Advanced Planning.

B.

They are created when an independent requirement is created for the finished product.

C.

They are created on assembly level during the planning run.

D.

They are only created for multilevel bill of material (BOM) structures

Questions # 5:

Mode selection is one of the scheduling options available with Advanced Planning in SAP S/4HANA. When can you use mode selection?

Options:

A.

When multiple production versions are maintained for one product

B.

When multiple operations are maintained for one product

C.

When alternative resources are used within one operation

D.

When multiple planned orders exist on one resource

Questions # 6:

Which master data object governs the relationship between supply source and demand source in the Kanban process?

Options:

A.

Replenishment strategy

B.

Production supply area

C.

Control cycle

D.

Rate routing

Questions # 7:

Which information is required when you create a product master in SAP S/4HANA?

Note: There are 2 correct answers to this question.

Options:

A.

Product type

B.

Selection screen for views

C.

Selection screen for plants

D.

Base unit of measure

Questions # 8:

What is the work center hierarchy in capacity planning?

Options:

A.

A group of work center in a parallel sequence that is used to split production quantities and work on them in parallel

B.

A group of alternative work centers providing a cumulative available capacity for production

C.

A group of work centers in a production line being used in sequence for production

D.

A group of alternative work centers for production, structured in hierarchy levels by priorities

Questions # 9:

What are the possible results of a production planning run in Advanced Planning (PP/DS)? Note: There are 2 correct answers to this question.

Options:

A.

Scheduling agreement schedule line

B.

Purchase Order

C.

Planned Order

D.

Production Order

Questions # 10:

Your production planners must execute planning only for specific resources. How can you achieve this in Advanced Planning (PP/DS)?

Options:

A.

Use a propagation range.

B.

Use a resource group

C.

Use a planning area.

D.

Use a planning group.