Questions # 1:

Scenario C: Dependencies and Product Backlog items

During Nexus Sprint Planning, representatives from each of the 9-member Scrum Teams

identify many dependencies. This makes it hard for them to choose the work they could pull

into their individual teams for the next Sprint. No matter how they reorganize the Product

Backlog items, they continually find more or new dependencies.

What would you recommend to the two teams that are continually dependent on each other to

help them manage their work?

(choose the best answer)

Options:

A.

The Nexus Integration Team should be responsible for integrating the work of these

two Scrum Teams.

B.

Reorganize these two Scrum Teams so that one is responsible for development and

one is responsible for integration.

C.

Merge the two Scrum Teams together.

D.

Ensure the appropriate representatives from both teams are present during Cross-

Team Refinement.

Questions # 2:

Which statements are true when multiple Scrum Teams work on a product at the same time?

(choose the best two answers)

Options:

A.

The different Scrum Teams coordinate their work to deliver a single Increment.

B.

Each Scrum Team develops one or more product components which the Nexus

Integration team uses to assemble the Integrated Increment.

C.

The Developers must integrate their work before the end of the Sprint.

D.

They are all on the same Scrum Team.

E.

The Scrum of Scrums assembles the components into an Integrated Increment.

Questions # 3:

Scenario B: Six Team Nexus with complex dependencies

A six team Nexus is developing a complex product, with different parts of the product that only

certain Scrum Teams can work on. In fact, there are some highly specialized individuals outside

the Nexus that are required for some of the work. In past Sprints the Nexus encountered

challenges dealing with the many dependencies between Scrum Teams.

Some individual Scrum Teams in this Nexus have said that they do not see how the work they

are doing is contributing to the product's progress. What is the best remedy for this situation?

(choose the best answer)

Options:

A.

During Nexus Sprint Planning, have all the teams plan the Sprint together in one

room, so they can see what other teams are working on.

B.

During Nexus Sprint Planning, ensure that all Scrum Teams understand the Nexus

Sprint Goal.

C.

Ask the Scrum Master to explain to the teams that the Product Owner can choose

which features to work on, as she has the final say.

D.

During Nexus Sprint Planning, ask each Scrum Team to create a Sprint Goal that

describes the purpose of the Sprint.

Questions # 4:

What is the purpose of the Nexus Sprint Retrospective?

(choose the best answer)

Options:

A.

To review the feedback from the Sprint Review and decide what actions to take.

B.

To ensure all Scrum Teams are working on the same improvement actions.

C.

To identify underperforming team members and recommend corrective action.

D.

None of the above.

Questions # 5:

True or False: There is one Product Backlog for a Nexus.

Options:

A.

True

B.

False

Questions # 6:

Scenario B: Six Team Nexus with complex dependencies

A six team Nexus is developing a complex product, with different parts of the product that only

certain Scrum Teams can work on. In fact, there are some highly specialized individuals outside

the Nexus that are required for some of the work. In past Sprints the Nexus encountered

challenges dealing with the many dependencies between Scrum Teams.

Which of the following two strategies would be most effective in dealing with their

dependencies?

(choose the best two answers)

Options:

A.

Discover and document dependent work during Cross-Team Refinement of the

Product Backlog, so teams are aware of dependencies before Nexus Sprint

Planning. This will allow Nexus Sprint Planning to focus on resolving

dependencies for the upcoming Sprint.

B.

Have the Nexus Integration Team order the Nexus Sprint Backlog. They should

control and resolve the dependencies.

C.

During Nexus Sprint Planning, have appropriate representatives from each team

in the Nexus briefly meet to discuss dependencies for the upcoming Sprint. This

conversation will help their individual team's Sprint Planning.

D.

Gather all people in the Nexus into a 48-hour Nexus Sprint Planning event.

Discover, document, and resolve dependencies during this time.

Questions # 7:

True or False: All Scrum Team members must attend the Nexus Daily Scrum.

Options:

A.

True

B.

False

Questions # 8:

The purpose of a Nexus Sprint Retrospective is to:

(choose the best two answers)

Options:

A.

Enable bottom-up intelligence to improve how the Scrum Teams in a Nexus are

working together.

B.

Provide a forum for management to see how the Nexus is performing.

C.

Allow for inspection and adaptation of both individual Scrum Teams and a

Nexus.

D.

Provide a single meeting to inspect and adapt how all Scrum Teams work

together.

Questions # 9:

A Nexus Daily Scrum:

(choose the best two answers)

Options:

A.

Provides a single meeting where all Scrum Teams can update the Sprint

Backlog.

B.

Is the same as a Scrum-of-Scrums.

C.

Provides input into each Scrum Team's individual Daily Scrums to help them

better plan their days work.

D.

Is only for the Nexus Integration Team to plan their work for the next 24-hours.

E.

Is an opportunity to make integration issues transparent.

Questions # 10:

Scenario C: Dependencies and Product Backlog items

During Nexus Sprint Planning, representatives from each of the 9-member Scrum Teams

identify many dependencies. This makes it hard for them to choose the work they could pull

into their individual teams for the next Sprint. No matter how they reorganize the Product

Backlog items, they continually find more or new dependencies.

What techniques could help this Nexus manage their dependencies effectively?

(choose the best two answers)

Options:

A.

The Nexus Integration Team should complete the dependent work ahead of the

Sprint for the teams.

B.

Reorganize team members between the teams to eliminate cross-team

dependencies.

C.

Extend the Sprint so that the teams can have more time to complete the

dependent work.

D.

Reorder Product Backlog items to better accommodate dependencies.