Questions # 51:

After collecting the control information on a light rail project within an original budget of 200.000 work hours, the construction contractor is ready for their monthly progress meeting with the client.

A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and 110.000 work hours paid. The stated progress by the contractor Is 60%.

What is the cost performance index (CPI)?

Options:

A.

BCWP/ACWP = 105.000/110.000 = 0.95

B.

ACWP/BCWP = 110.000/105,000 = 1.05

C.

BCWS/ACWP = 100.000/110.000-0 91

D.

ACWP/BCWS = 110,000/100.000- 1.10

Questions # 52:

A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.

Assuming the average life span of a lithium battery is two years and is normally distributed with a standard deviation of two months, what is the probability the battery will last between 20 months and 26 months?

Options:

A.

82%

B.

75%

C.

90%

D.

84%

Questions # 53:

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

The latest allowable end time minus the earliest allowable end time on a schedule activity is referred to as:

Options:

A.

Activity total slack

B.

Remaining duration

C.

Just-in-time" scheduling

D.

Free float

Questions # 54:

Question # 54

The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

What is the cost of manufacturing labor for the piece of equipment today?

Options:

A.

$140,000

B.

$875,000

C.

$210,000

D.

$105,000

Questions # 55:

A schedule's late dates are calculated during the:

Options:

A.

Loop calculations

B.

Backward pass

C.

Forward pass

D.

Float

Questions # 56:

When the project plan is implemented:

Options:

A.

Activities are carefully monitored and controlled against the baseline

B.

The basis for payment applications is formalized

C.

The forward and backward pass is identified

D.

CPI and SPI can be calculated and reported