Questions # 11:

A project manager has been asked to work on a cross-departmental company-wide initiative. There will be many individuals assigned to each task.

What should the project manager ask users to do when it comes to completing tasks?

Options:

A.

Users do not need to complete tasks when multiple users are assigned.

B.

Mark the task as "Done with my part."

C.

Make an update and tag the project manager.

Questions # 12:

Due to a time sensitive shift in priorities, the timeline of a project needs to be adjusted. What step should the Project Owner take before adjusting the task timeline to avoid sending notifications to the project team?

Options:

A.

Update the project status.

B.

Recalculate the project timeline.

C.

Update the project baseline.

Questions # 13:

A project sponsor has asked to see a summary of all projects that they are the sponsor of which were completed in the past year. The project sponsor wants to see the information grouped by the month the project was completed. What steps should the project manager take to create this view?

Options:

A.

Visit the Reports page and create a Project report. In the filter, update the actual completion date value to "past year" and update the Project Sponsor ID field to the project sponsor’s name. In the grouping tab, add a grouping for the actual completion date. In the Group Dates by field, select "month."

B.

Visit the Reports page and create a Project Sponsor report. In the filter, update the actual completion date value with custom dates for the past year and update the Project Sponsor ID field to the project sponsor’s name. In the grouping tab, add a grouping for the planned completion date. In the Group Dates by field, select "month of year."

C.

Visit the Dashboards page and create a Project report. In the filter, update the actual completion date value to "past year" and update the Project Sponsor ID field to the project sponsor’s name. In the grouping tab, add a grouping for the actual completion date. In the Group Dates by field, select "month of year."

Questions # 14:

A project manager is assigned to a new Workfront request. The request specifies that themanagement team’s sign-off is needed before the project can begin.

What is the appropriate action for the project manager to take?

Options:

A.

Convert the issue into a project using a project template.

B.

Email the management team and request their approval.

C.

Use a customized approval process to route the issue for approval.

Questions # 15:

What are two ways to associate milestone steps to tasks? (Choose two.)

Options:

A.

In-line editing a task list on a project

B.

From the Milestone View in the Projects area

C.

Through bulk-editing multiple tasks

D.

In the settings area of a task

Questions # 16:

All of the tasks on a project show as 100% complete, but when the Project Owner tries to update the status of the project to Complete, the Owner receives an error that reads "Project cannot be marked Complete if there are open issues and tasks that are not complete." How can the Project Owner determine which tasks are incomplete?

Options:

A.

There are incomplete approval workflows on one or more tasks. The Project Owner could filter the project task list for incomplete tasks and check the task status to determine which tasks are not complete.

B.

There are incomplete issue predecessors that need to be resolved. The Project Owner can navigate to the project issues section in the left navigation pane to see the incomplete items.

C.

The task status needs to be updated to Done even though the percent complete is at 100%. The Project Owner could filter the project task list for incomplete tasks and check the task status to determine which tasks are not complete.

Questions # 17:

A portfolio manager has inadvertently given too much access to all the projects in their portfolio to Program Manager A.

How does the portfolio manager rectify the situation to ensure that Program Manager A has Manage access only on their own program?

Options:

A.

Share the program with Program Manager A with Manage access and ensure the system administrator adjusts Program Manager A's access level.

B.

Share the program with Program Manager A with Manage access and ensure Program Manager A understands they cannot manage the rest of the portfolio.

C.

Share the program with Program Manager A with Manage access and remove Program Manager A's Manage access on the portfolio.

Questions # 18:

Which two statements are true about Groups and Teams? (Choose two.)

Options:

A.

A Team can be assigned to a task, but a Group cannot be assigned to a task.

B.

Objects can be shared with either a Group or a Team.

C.

A Group can be assigned to a task, but a Team cannot be assigned to a task.

D.

Work requests can be routed to either a Group or a Team.

Questions # 19:

What are two characteristics of a Group in Workfront? (Choose two.)

Options:

A.

A Group can be tagged in an Update thread communication.

B.

A Group assignment is not required for a user.

C.

A Group can be associated with a Company or a Project.

D.

A user can be assigned as Group Administrator of a Group.

Questions # 20:

Task 1 on Project 1 can only be started once the final milestone on Project 2 is completed.

How can the project manager configure this relationship?

Options:

A.

Add a cross-project predecessor on the final milestone of Project 1.

B.

Add a cross-project predecessor on Task 1 in Project 1.

C.

Add a cross-project predecessor on the final milestone in Project 2.