Questions # 11:

According to the 'change formula' (Beckhard and Harris), which response will increase the desirability to an individual of the proposed change or end state?

Options:

A.

Focus on the benefits of the change.

B.

Communicate the 'burning platform.'

C.

Clarify the steps users need to take.

D.

Put mitigations in place to reduce risk.

Questions # 12:

How should DSDM team measure progress?

Options:

A.

Through a project dashboard

B.

Based on what has been delivered at the end of a Timebox.

C.

Based on the completion of activities rather than the delivery of products

D.

Through an analysis of the Instrumental Success Factors.

Questions # 13:

What phase will decide on which projects are started, based on a clearly defined objective?

Options:

A.

Pre-Project

B.

Feasibility

C.

Foundations

D.

Post-project

Questions # 14:

How is contingency typically managed in a DSDM project?

Options:

A.

Not needed in a DSDM project.

B.

Allowed adding a percentage to the high-level estimates.

C.

Managed by varying the features to be delivered.

D.

Managed by varying time and cost

Questions # 15:

Which statement applies to the DSDM process?

Options:

A.

Can be configured and calibrated to cater for light or strong governance

B.

DSDM projects can deliver the phases in the DSDM process in any order

C.

Does not require the elaboration of supporting products for complex projects

D.

Provides an approach that can be used for all projects without change

Questions # 16:

When building a change delivery scorecard, which of the different views on value are achieved through a measurable increase in sales?

Options:

A.

Financial.

B.

Customer.

C.

Internal.

D.

Learning & Growth.

Questions # 17:

What is the MoSCoW technical used for?

Options:

A.

Understanding and managing priorities.

B.

Ensuring a team-based approach through visual and verbal communication and collaboration.

C.

Creating a visual representation of a problem or a solution.

D.

As an opportunity to share information across the team and to do any day.to.day re-planning and reorganizing as necessary when issues occur.

Questions # 18:

What role normally facilitates the Daily Stand.up?

Options:

A.

Business Advisor

B.

Technical Advisor

C.

Team Leader

D.

Project manager

Questions # 19:

Which of the common Agile concepts, behaviors, and techniques delivers a version of a product with just enough features to be usable by early customers who can then provide feedback for future product development?

Options:

A.

Minimum viable product.

B.

Full transparency.

C.

Self-organized teams.

D.

Empowerment.

Questions # 20:

Social neuroscience summarizes five brain processes involved in social situations using the mnemonic SCARF. What does the ‘F’ represent?

Options:

A.

Fairness.

B.

Faith.

C.

Fear.

D.

Fight.