Questions # 1:

Which of the following is a management practice that will provide business continuity?

Options:

A.

Creating and documenting a business continuity’ plan

B.

Defining an organizational policy for business continuity

C.

Analyzing and assessing the organization for business continuity’

D.

Identifying and selecting appropriate strategies for business continuity

Questions # 2:

When a software qualm- engineer is preparing an inspection report to present to management., what type of information should be included in the report?

Options:

A.

A summary- of the inspection results

B.

A summary- of the defects found by each inspector

C.

A detailed analysis of the results for each inspection

D.

A list of actions that management should take to correct the defects

Questions # 3:

During an audit, the lead auditor’s primary responsibility is to

Options:

A.

decide which procedures are to be audited

B.

collect data and materials presented during the audit

C.

keep the audit team focused on the audit scope

D.

develop and distribute the audit checklist

Questions # 4:

Which of the following types of tests should be run on an installation of a new client server development environment that has 2 to 25 users in order to ensure it meets the company ' s requirements?

Options:

A.

Maintainability tests

B.

Boundary value tests

C.

Efficiency tests

D.

Performance tests

Questions # 5:

In order to reduce inconvenience for customers during a maintenance phase, support staff should concentrate on fixing

Options:

A.

all known defects

B.

minor defects only

C.

defects that affect the “vital few” customers

D.

defects that impact essential operations

Questions # 6:

A project manager has decided to modify a project schedule to allow some of the low-level design to begin before all of the high-level design has been completed. Is this approach appropriate?

Options:

A.

No, because high-level design must be completed before low-level design is started.

B.

Yes, provided the same people perform both the high-level and the low-level designs.

C.

Yes, provided the activities have a relationship to one another.

D.

Yes, provided no unfinished high-level design will impact a specific area to be low-level designed.

Questions # 7:

Which of the following benefits is related to DevOps when it is used to facilitate development activities?

Options:

A.

Reducing time to market

B.

Minimizing software releases

C.

Increasing return on investment

D.

Standardizing organizational processes

Questions # 8:

If 5 defects were found during a software analysis and 5 defects were found in later phases, what is the phase containment effectiveness (PCE) of this software analysis?

Options:

A.

0%

B.

25%

C.

50%

D.

100%

Questions # 9:

Which of the following statements is true about component reuse?

Options:

A.

The more a developer knows about the implementation, the more reusable a component will be.

B.

Information-hiding impedes the development of reusable components.

C.

Development costs are improved by reusable components.

D.

Modifying a previously used module is an example of module reuse.

Questions # 10:

Which of the following roles acts as the final arbitrator for any audit-related issues that cannot be handled at a lower level?

Options:

A.

The client

B.

The auditee

C.

Lead auditor

D.

Auditee management