Questions # 1:

Which of the following is not a key decision when defining a project test strategy?

Options:

A.

Selection of test tools

B.

Selection of test levels

C.

Selection of test types

D.

Selection of test techniques

Questions # 2:

During a test process improvement initiative, defect information is gathered to perform defect cluster analysis.

Which aspect is most likely being targeted for improvement?

Options:

A.

To improve the defect removal efficiency.

B.

To reduce the total number of defects.

C.

To better understand risk and focus testing, as part of risk-based testing.

D.

To minimise the costs associated with defects.

Questions # 3:

Which of the following is not true regarding applying a model-based approach, e.g., TMMi, for improvements at project level?

Options:

A.

The assessment should include test management processes such as test planning and test monitoring and control

B.

The assessment should include test engineering processes such as test design, test implementation and test execution

C.

The assessment should include areas such as test policy and test organisation

D.

Practices at organisational level should be tailored appropriate to the project's context

Questions # 4:

Your company is considering purchasing a test tool suite from a respectable vendor. Your manager has searched the internet for comparable products, but none of them meet his specific requirements. A tool demonstration has been arranged for next week and your team has been invited to attend. The tool suite consists of a test management tool, test execution tool, and a requirements management tool. There is a possibility of adding a performance testing tool at a later stage.

You have decided to attend the demo but raise some issues beforehand regarding expectations.

Which two issues from the options provided below should at least be raised?

Options:

A.

What are the problems we are trying to address?

B.

Do we have a set of tool requirements to validate the tool against?

C.

How will the implementation be organised?

D.

Which project will be selected to perform the tool pilot?

E.

Is customized training available?

Questions # 5:

You are a tester working in an Agile team in the finance domain. The team consists of 6 members, and you are the only tester. The team is responsible for the development and maintenance of a mobile front-end application. The application is considered to be critical with respect to customer impact and market branding.

You have been asked to identify which test management activity needs to be performed within the team to enhance test maturity and achieve a higher level of product quality.

Which test management activity would you recommend the team should adopt?

Options:

A.

Define quality criteria for user stories and acceptance criteria

B.

Provide detailed estimations early for each test level

C.

Perform product risk identification and analysis

D.

Increase coverage by automating more tests

Questions # 6:

In an Agile context, defects are often fixed without writing a formal defect report. However, there are some conditions where it is good practice to write a defect report, even in an Agile context.

When is a defect report typically not written in an Agile context?

Options:

A.

A defect that is blocking other iteration activities and cannot be immediately solved

B.

A defect that cannot be solved in the same iteration

C.

A defect that must be resolved by or in co-operation with other teams

D.

A defect that is found for a high-priority user story

Questions # 7:

Factors that are important to take into account when performing test estimation include:

i. The quality of the test basis

ii. The availability of test automation

iii. The amount of rework required

iv. The distribution of testing across several locations

The various factors can be grouped by characteristic. Examples of characteristics include:

Options:

A.

Test context

B.

Test results

C.

Product

D.

Development processWhich factor is related to which characteristic?

E.

A = i, B = ii, C = iii, D = iv

F.

A = iv, B = iii, C = i, D = ii

G.

A = iv, B = iii, C = ii, D = i

Questions # 8:

The following defect management process is in use at a company… What is the most important recommendation you would make for the defect report template in this process?

Options:

A.

Automate the incident numbering

B.

Add a classification field for the type of incident

C.

Add a lifecycle phase field to document when the defect is found

D.

Add a priority field to show how quickly it needs fixing

Questions # 9:

Management is sceptical regarding the budget request (€25,000) for the next testing project. You are asked for a cost-benefit calculation. Based on historical data from several projects, you have come up with the following numbers:

Average prevention cost per defect: €200

Average cost of detection per defect: €400

Average cost of internal failure: €150

Average cost of external failure: €2,500

Expected number of defects to be found in this project during testing: 50

What is the result for the expected cost-benefit calculation for the upcoming project?

Options:

A.

€62,500

B.

€72,500

C.

€87,500

D.

€92,500

Questions # 10:

Which of the following activities in the test process is considered to deliver a document which can be used as a major input for test process improvement?

Options:

A.

Test Planning

B.

Test Monitoring

C.

Test Execution

D.

Test Completion