Sally is negotiating with an oversea supplier on the price and payment period. Her company and the supplying organisation are equal in bargaining power. The supplier says that they are investing in new facilities and machinery so the payment period should not be longer than 30 days. Sally knows that her company often pays the suppliers after 45 days from the delivery, but at the moment the company has positive cash flow and it is able to pay immediately. Which of the following should be Sally's concession plan?
In a negotiation for a new contract, the supplier suggests the buyer to shorten payment period from 45 days to 15 days because they are investing in new facilities to expand the supply capacity. The buyer replies that she can only sign off the deal if the payment period is 30 days ormore since it often takes at least 30 days for her company to collect the payment from customers. A permission from senior management is required for this suggestion. In order to ensure that supplier understands the matter, she reiterates it throughout the meeting. Which tactics is she using?
1. Outrageous initial demand
2. Salami slicing
3. Lack of authority
4. Broken record
Which of the following is the best description of direct cost?
A public agency opens a tendering process for a road building project that lasts approximately 1 year. They post their requirements on public journal and receive some interests. After conducting due diligence process and selecting the lowest bidder, the project commences. However, the supplier complains that price of material increases because of a shortage of supply, then they demands an 5% uptick in contract value. The agency investigates the increment and sees that there is indeed a fluctuation in prices of supplier's input. They are likely to accept the proposal, but they are also concerned that supplier may demand more. To avoid making another concession with the supplier, which of the following should be a priority action of the agency?
Fast & Easy Limited, a global fast food retailer, is in a negotiation with its major meat supplier. The supplier is asking for a 2% price increase, which Fast & Easy is strongly resisting. The supplier justifies this increase by stating that currency fluctuations, an unstable economic climate, and rising transport costs have necessitated this increase. Which influencing tactic is the supplier using?
Where can we find the data on macroeconomics?
1. From trade journal
2. From supplier's marketing catalogue
3. From stock exchange market
4. From government's statistics
A procurement manager has decided to bring in a junior member of their team to a negotiation meeting. Which of the following would be suitable roles for this junior member of the team?
Note taker
Expert
Observer
Chair
Ma Bell was the sole provider of landline telephone service to most of the US in 1980s. This is an example of...?
There are many factors which will influence supplier pricing decisions. Which of the following are external factors that may apply? Select THREE that apply:
A procurement manager has decided to bring in a junior member of their team to a negotiation meeting. Which of the following would be suitable roles for this junior member of the team?
Note taker
Expert
Observer
Chair