Questions # 61:

A supplier wishes to develop a new blood collection system for healthcare but needs to work with a clinical expert to develop the device. Why would a partnership be the best approach?

Options:

A.

To keep costs down

B.

It is a technically complicated supply

C.

Because it is a low-risk supply

D.

To gain market share

Questions # 62:

Danny is procuring a new IT software, which he doesn’t know much about. He has done a bit of research on the internet but is still unsure how much he can expect to pay. What should be Danny’s next step?

Options:

A.

Issue a RFI

B.

Issue a RFQ

C.

Issue an ITT

D.

Issue an OJEU

Questions # 63:

A software developer is seeking to develop a new fitness trends app. They are looking to create a contract with a fitness expert to give advice on the type of changing fitness trends. What agreement should the app developer aim to achieve?

Options:

A.

Partnering relationship

B.

Cost-based relationship

C.

Quality-based relationship

D.

Traditional contracting relationship

Questions # 64:

Which of the following documents would you expect a supplier to submit as part of a Request for Proposal? Select THREE

Options:

A.

Full pricing information

B.

Liquidity Ratio

C.

Risk Assessments

D.

Method Statements

E.

Gearing Ratio

Questions # 65:

Achieving value for money can often be described as the three Es? What are these?

Options:

A.

Ethics, Environment, Economy

B.

Economy, Efficiency, Environment

C.

Efficiency, Economy, Ethics

D.

Effectiveness, Efficiency, Economy

Questions # 66:

A partnership was created between a company and one of its local suppliers when the managing directors of each company met and thought partnering could be a good idea. No other departments were included in the discussions. The partnership has been in place for over a year, but neither of the companies has achieved any additional benefits. The company has been unable to offer any increased business to the supplier, and the supplier has been unable to improve on the quality of its products. The partnership is going to be terminated. What is a possible main reason for the failure of the partnership?

Options:

A.

Poor planning

B.

Market changes

C.

Distance barrier

D.

Cultural differences

Questions # 67:

An automotive company has hired Tom as the procurement manager. Tom is to manage a team of two people who have worked in the department for a number of years. Conflict exists between the two members of staff due to an overlap of responsibilities. Which of the following processes would be most appropriate for Tom to use to reduce this conflict?

Options:

A.

Tom could avoid mentioning the conflict and hope that it is resolved without action

B.

Tom could hire an additional member of staff to take on some of the duties

C.

Tom could restructure the team so both members do not have to work together

D.

Tom could arrange a meeting and set performance targets for each member

Questions # 68:

Grey Stone Memorial Hospital is a private medical facility which has an idea for a vaccine to a deadly disease, but does not have the capacity to make the vaccine itself. It is considering partnering with a well-known pharmaceutical company in order to bring the vaccine to market. What is the biggest risk to Grey Stone?

Options:

A.

Intellectual Property Rights

B.

Increased Costs

C.

Low quality product

D.

Uninformed stakeholders

Questions # 69:

Andrew runs a factory that makes cakes. Vanilla Extract is a vital ingredient in Andrew’s cakes and this is a monopolistic market. Andrew has noticed recently that the quality of the supplier’s product has reduced, and this has led to several complaints from customers. Andrew is considering entering into a Partnership with this supplier as he believes this will help increase the supplier’s performance. Is this the correct thing to do?

Options:

A.

Yes- partnership sourcing can improve performance which will ultimately satisfy the end customer

B.

Yes- partnership sourcing will improve sales figures

C.

No- Andrew should use an alternative supplier

D.

No- Andrew should outsource the vanilla extract.

Questions # 70:

National Hospital Trust (NHT) has entered into a partnership relationship with a major facilities management provider. The two organizations have agreed on the approach to undertake regular reviews and audits. The audit approach will include which of the following?

Options:

A.

Category management and supplier rationalization

B.

Specification development and management

C.

Lessons learned and continuous improvement

D.

Macro and micro environmental analysis