To create a new Project that is similar to a current active project, you should...?

The system sends a notification to the person who is assigned to a task when...
What types of Objects can be included as content into Routes?
Once a project budget has been promoted to Plan Frozen:
A project budget can be imported from what type of file directly?
Who can create a project template?
Looking at the below image, when would you expect to work on the Create Instructor Guide task (WBS 2.4) by looking at the Dependency column?

Your project has a task called Create Student Guide (Task #3) which CANNOT start until Review Course Outline (Task #2) finishes. What is the correct dependency code?
When creating a Route, if Approve is selected in the Action field, the task assignee must:
If you wanted to view the details of a Program in a new window, what would you do?