Questions # 21:

Match each component of the VxRail HCI System Software to its description.

Question # 21

Options:

Questions # 22:

A systems engineer is performing a VxRail upgrade in a VMware Horizon VDI cluster All hosts are put in Maintenance Mode.

What action does the engineer need to perform on each host once the upgrade has been completed?

Options:

A.

From the Connection Server run IcMaintcmd to delete the parent VMs and exit Maintenance Mode for each host

B.

From the Connection Server, run IcMaintcmd to take the hosts out of Maintenance Mode and reboot them

C.

Set the InstantClone Maintenance annotation value to the original value

D.

Set the InstantClone Maintenance annotation value to 2

Questions # 23:

An implementation engineer needs to validate the VxRail network configuration. Where can they obtain the NVT for VxRail?

Options:

A.

Dell Technologies Central

B.

Dell Technologies Information Hub

C.

Dell VxRail Expert Channel

D.

Dell VxRail Fast Pass

Questions # 24:

According to the VxRail PEQ Engagement Details worksheet, links to what resources should the SE send to the customer?

Options:

A.

VxRail vCenter Server Planning Guide

Network Validation Tool

B.

VxRail vCenter Server Planning Guide

VxRail Network Planning Guide

C.

VxRail QuickStart Guide

VxRail Network Planning Guide

D.

VxRail QuickStart Guide

Network Validation Tool

Questions # 25:

An implementation engineer is deploying a new VxRail cluster What should they confirm before installing the hardware?

Options:

A.

At least 24 in (61 cm) of clearance exists in front of and behind the cabinet

B.

Redundant power zones exist with adequate power cables

C.

Power distribution supports only the power rating of a single node

D.

Service laptop is on the same IP network as the iDRACs

Questions # 26:

What is the minimum number of VxRail nodes required for a vSAN storage policy with RAID-5 (Erasure Coding)?

Options:

A.

3

B.

4

C.

5

D.

6

Questions # 27:

A VxRail D560 cluster was delivered six months ago and now needs to be prepared for installation with the target code. What is the correct method to complete the task?

Options:

A.

Boot into RASR ISO and perform a RASR Reset

B.

Boot into RASR USB and perform a RASR Reset

C.

Boot into SD card and perform a Factory Reset

D.

Boot into RASR ISO and perform a Factory Reset

Questions # 28:

An implementation engineer is in the validation phase of a VxRail deployment with two Dell EMC ToR switches. Which command should they run on each of the ToR switches to validate that Link Aggregation has been configured according to Dell best practices for VxRail node interfaces?

Options:

A.

show network-policy profile

B.

show interface status

C.

show port-channel summary

D.

show interface

Questions # 29:

Match each VxRail API request with the information to be retrieved.

Question # 29

Options:

Questions # 30:

How must node ports on Dell EMC ToR switches be configured when the Spanning Tree Protocol is enabled in an environment?

Options:

A.

In Port-Channel mode

B.

In Forwarding status

C.

As edge ports

D.

As access ports