Under both FIDIC Yellow Book (YB) and Silver Book (SB) (edition 1999), if the Engineer (YB) / Employer (SB) instructs the Contractor based on Sub-Clause 8.6 to provide a revised programme, the acceptance by the Engineer (YB) / Employer (SB) of a revised programme with a completion within Time of Completion entitles the Contractor to a payment of the needed extra costs. Is this statement true or false?
Which one of the following is NOT considered a change made in the 2017 edition of the FIDIC Red, Yellow, and Silver Books?
Which two statements are correct regarding the FIDIC Red Book (edition 2017)?
Which one statement is correct regarding the FIDIC Red Book (edition 2017)?
If the Engineer is required to obtain the Employer's prior approval to issue determinations (including such requirement in the Particular Conditions) and such approval was not given by the Employer, what possible options are at stake for the Engineer to proceed? [1999 Edition] (2 correct answers apply)
Choose all of the correct answers (multiple possibilities).
You are the Contract Manager of the Engineer in a hotel project. In May 2020, the Employer and the Contractor signed a Contract based on the FIDIC Yellow Book (edition 2017), as per which the Contractor will design and build a hotel project with Contract Price of 5,100,000 USD. The Time for Completion for this project is 12 months (May 2021). The Contract also named a nominated Subcontractor (as referred to in Sub-Clause 4.5) who provides mechanical, electrical, and plumbing services for the project (including the fire fighting system), which was accepted by the Contractor without any discussions.
The Project was delayed due to issues with the fire fighting system, and you issued the Taking-Over Certificate in June 2022.
The Employer sent a Notice of Claim to the Contractor on Delay Damages with a maximum value equal to 10% of Contract Price (510,000 USD). The Employer also gave a Notice to the Contractor stating that the Contractor has failed to submit the evidence of payment to the nominated Subcontractor as well as the reason for withholding payment to the nominated Subcontractor. Therefore, the Employer has paid the nominated Subcontractor directly the entire amount due, coming to 100,000 USD. The Employer intends to include this amount as a deduction in the Final Payment to the Contractor.
As Contract Manager of the Engineer, you are tasked to make a fair determination of the Notices of the Employer. In your "Notice of the Engineer's determination", what is your determination for the deduction of the next Interim Payment to the Contractor in relation to the amount directly paid to the nominated Subcontractor?
The FIDIC Books are evolutions of earlier contract models, and although the different versions of a specific model are not the same, familiarity in definitions and structure makes it easier to work with different FIDIC books as well as with their different editions.
Is this statement true or false?
Under the FIDIC Red Book, which one of the following statements is correct for a claim by the Contractor?
In case a Variation is initiated by the Engineer for prompt implementation ...... [FIDIC Red, and Yellow Books, 2017 Editions]
Choose all of the correct answers (multiple possibilities).