Questions # 21:

Under both FIDIC Yellow Book (YB) and Silver Book (SB) (edition 1999), if the Engineer (YB) / Employer (SB) instructs the Contractor based on Sub-Clause 8.6 to provide a revised programme, the acceptance by the Engineer (YB) / Employer (SB) of a revised programme with a completion within Time of Completion entitles the Contractor to a payment of the needed extra costs. Is this statement true or false?

Options:

A.

True

B.

False

Questions # 22:

Which one of the following is NOT considered a change made in the 2017 edition of the FIDIC Red, Yellow, and Silver Books?

Options:

A.

The concentration on dispute avoidance, including an enhanced role for the Dispute Avoidance and Adjudication Board (DAAB) in this respect, and promoting cooperation between the parties during the project.

B.

New procedures requiring the Contractor to prepare and implement a Quality Management System to show compliance with the Contract requirements.

C.

A fair and balanced approach where risk is allocated to the Party that is best able to bear and control that risk.

D.

New procedures requiring the Contractor to prepare and implement a Compliance Verification System to show that the design, materials, workmanship and certain other matters all comply.

Questions # 23:

Which two statements are correct regarding the FIDIC Red Book (edition 2017)?

Options:

A.

Words and expressions stated in Sub-Clause 1.1 Definitions do not apply in respect of Specifications and Drawings.

B.

Contract Data contains information which is required by certain Sub-Clauses in the General Conditions.

C.

There is never a difference in effect whether in the Particular Conditions when the term "Works" is used, or when the term "works" is used.

D.

In some cases, if a certain information is not provided in the Contract Data, the relevant Sub-Clause shall not be applicable.

Questions # 24:

Which one statement is correct regarding the FIDIC Red Book (edition 2017)?

Options:

A.

Instructions to Tenderers are part of the Employer's Requirements.

B.

No Data other than required by the General Conditions of Contract may be entered in the Contract Data.

C.

Instructions to Tenderers may require the tenderer to provide information on matters in Sub-Clause 4.3 on Contractor's Representative and Sub-Clause 6.12 on Key Personnel.

D.

General Conditions of Contract cannot be amended as it may imbalance the obligations and rights of the Parties.

Questions # 25:

If the Engineer is required to obtain the Employer's prior approval to issue determinations (including such requirement in the Particular Conditions) and such approval was not given by the Employer, what possible options are at stake for the Engineer to proceed? [1999 Edition] (2 correct answers apply)

Choose all of the correct answers (multiple possibilities).

Options:

A.

Remain silent and not do anything in the subject.

B.

The Engineer should refer the matter in subject to the DAB.

C.

Issuing the determination to the Contractor in the form and with the content agreeable to the Employer, with a remark, that it is the Employer's determination and not the Engineer's determination.

D.

Informing the Contractor of their inability of issuing the determination, in lack of the Employer's necessary approval.

Questions # 26:

You are the Contract Manager of the Engineer in a hotel project. In May 2020, the Employer and the Contractor signed a Contract based on the FIDIC Yellow Book (edition 2017), as per which the Contractor will design and build a hotel project with Contract Price of 5,100,000 USD. The Time for Completion for this project is 12 months (May 2021). The Contract also named a nominated Subcontractor (as referred to in Sub-Clause 4.5) who provides mechanical, electrical, and plumbing services for the project (including the fire fighting system), which was accepted by the Contractor without any discussions.

The Project was delayed due to issues with the fire fighting system, and you issued the Taking-Over Certificate in June 2022.

The Employer sent a Notice of Claim to the Contractor on Delay Damages with a maximum value equal to 10% of Contract Price (510,000 USD). The Employer also gave a Notice to the Contractor stating that the Contractor has failed to submit the evidence of payment to the nominated Subcontractor as well as the reason for withholding payment to the nominated Subcontractor. Therefore, the Employer has paid the nominated Subcontractor directly the entire amount due, coming to 100,000 USD. The Employer intends to include this amount as a deduction in the Final Payment to the Contractor.

As Contract Manager of the Engineer, you are tasked to make a fair determination of the Notices of the Employer. In your "Notice of the Engineer's determination", what is your determination for the deduction of the next Interim Payment to the Contractor in relation to the amount directly paid to the nominated Subcontractor?

Options:

A.

The Employer is entitled to deduct the amount directly paid.

B.

The Employer is not entitled to deduct the amount directly paid.

Questions # 27:

The FIDIC Books are evolutions of earlier contract models, and although the different versions of a specific model are not the same, familiarity in definitions and structure makes it easier to work with different FIDIC books as well as with their different editions.

Is this statement true or false?

Options:

A.

True

B.

False

Questions # 28:

Under the FIDIC Red Book, which one of the following statements is correct for a claim by the Contractor?

Options:

A.

The Employer has the authority to accept a claim by the Contractor, even in the case of the Contractor's failure to comply with the notice requirements.

B.

If the Engineer does not make a determination, the Employer and the Contractor are unable to agree to settle an issue that gave rise to a claim.

C.

The Engineer's response to the Contractor's submission of detailed particulars that are required by the procedure for claims by the Contractor must include the Engineer's final decision on the quantum.

D.

It is the Employer's Representative who must first respond to the claim by the Contractor.

E.

The Engineer's response to a claim by the Contractor is final and binding upon the Employer.

Questions # 29:

In case a Variation is initiated by the Engineer for prompt implementation ...... [FIDIC Red, and Yellow Books, 2017 Editions]

Choose all of the correct answers (multiple possibilities).

Options:

A.

... the Contractor may send a Notice to the Engineer, that the subject of the Variation was Unforeseeable (having regard to the scope and nature of the Works), hence, the Contractor is not to start implementing the varied work promptly.

B.

... the Contractor is required to commence implementing the varied works and take records of all the details ( ... regarding the details of the varied works executed, expenditures incurred, and impact on progress etc.)

C.

... the Contractor is required to commence implementing the varied works even if it would pose immediate hazard to the safety of public areas surrounding the Site

D.

... the Contractor within 28 days after receiving such instruction shall submit to the Engineer a description of the varied work, a programme for its execution and a proposal for adjustment of the Contract Price.

E.

... the Contractor is not bound to start implementing the varied works right up until the price for the varied works is fully agreed (or determined)