Questions # 101:

Which of the following options is a factor to consider in designing for cost on the cloud?

Options:

A.

Scaling policy settings

B.

Instance specifications

C.

Select

D.

Instance type as calculation method

Questions # 102:

HUAWEI CLOUD game O&M and log analysisscheme. Which of the following cloud services is generally involved?Multiple selection

Options:

A.

Cloud supervisor ridicule GengwuTHOSE

B.

Application Performance Management Service APM

C.

Log Analysis Service LTS

D.

Data encryption service DEW

Questions # 103:

Options:

Questions # 104:

When migrating applications to the cloud there are many factors that affect the migration efficiency. When using an online migration solution, the most important factors affecting migration efficiency include migration network bandwidth and network quality, the performance of source and destination hosts, the time period during which the migration work is carried out, the types of migration services, the types of migration databases, and migration tools. Judgment

Options:

A.

True

B.

False

Questions # 105:

Which of the following scenarios describes the x-axis horizontal scalability of an AKF expansion cube? (Many)

Options:

A.

An Internet company has a surge in the number of users, and the users are distributed in multiple regions, and multiple clusters are established in Beijing, Shanghai, Sichuan and other places according to the areas where the users are distributed

B.

The passenger access volume of a taxi application increases, and the passenger services in the taxi application are independently separated and expanded as needed

C.

In order to ensure the reliability of datA. a financial enterprise deploys a database in the active and standby mode to achieve high reliability of the database

D.

An e-commerce application runs multiple instances during peak business hours and load balances front-end traffic through clustering

Questions # 106:

The construction of government cloud needs to build the process and system of cloud services, the following description of the process and system, which are the correct items?

Options:

A.

Smooth migration of F-based services

B.

Distributed cloud DC architecture

C.

Physical dispersion, logical set

D.

Cloud service executioner and XieJie system

Questions # 107:

When you use HUAWEI CLOUD SMS to migrate wind ows hosts, you use the block of the file system as the basic unit Migration only the valid block data is migrated to the destination server, thereby improving the migration efficiency. Judgment

Options:

A.

True

B.

False

Questions # 108:

The goal of ( ) is to achieve the management of project resources, calculate the cost of each project, and transparent cost management. Answer: Cost labels

1.Application O&M management AOM In the log related functions are provided by()Provide and report the call list.(Fill in the English abbreviation)

Options:

Questions # 109:

Apply performance data for APM and which of the following services can provide performance data input? Multiple selection

Options:

A.

Cloud performance testingCPTS

B.

Cloud measurement CloudTest

C.

Application operation and maintenance WSAOM

D.

machine learning service MLS

Questions # 110:

In HUAWEI CLOUD latency refers to the time it takes for a call to initiate a request to obtain a response. In APM, the overall delay refers to the total time spent on the entire request, and the service delay refers to the time spent on a single service, that is, the overall time consumption minus the time spent calling other installation probe services. There are services A. B, C A calls B

, and B calls C. What are the correct items for the following description of the delay of each service? Multiple selection

Question # 110

Options:

A.

A service overall delay = TA. service delay = Ta-Tb1 -Tb2-Tco

B.

B service overall delay = Tb1 + Tb2 + TC. service delay = female.

C.

A service overall delay = Tb1 + Tb2 + TC. service delay = ratio 1 + Tb2

D.

B service overall delay = Tb1 + Tb2 + TC. service delay = servant 1 + Tb2