Questions # 11:

A firm engaging in low-cost country sourcing wants to assume the least amount of risk when importing goods into its own country. Which of the following Incoterms® 2020 rules would be MOST useful in achieving this goal7

Options:

A.

CFR

B.

CPT

C.

EXW

D.

DAP

Questions # 12:

In preparation for a new product launch, a company reviews the production capabilities of several regional plants in comparison with anticipated demand. Plant A is expected to have the highest demand, but consistent supply of parts is less reliable there than in other locations. The firm locates a supplier near the plant, which, although qualified, currently does not have enough space to store the large volume of finished parts Plant A will need for production. However, this supplier plans to expand.

To support plant operations during new product ramp-up, which of the following is MOST likely to be effective?

Options:

A.

Expand Plant A's warehouse space so it can maintain higher safety stock levels

B.

Engage a warehouse provider near Plant A to hold safety stock

C.

Procure additional safety stock at another plant and ship to Plant A

D.

Contract with multiple suppliers to support Plant A's operations

Questions # 13:

Which of the following is the MOST important reason for establishing and maintaining a supplier quality certification program?

Options:

A.

Quality champions from both the buyer and seller will have better opportunities to communicate.

B.

Supplier payments should be closely tied to maintaining quality standards.

C.

A supplier quality certification program is necessary for the development of a supplier scorecard.

D.

Certification programs keep suppliers focused on quality elements important to the customer.

Questions # 14:

A manufacturer is concerned that excess packaging materials used for a product will send the wrong message to consumers who may have selected the product based on its sustainable design. How can supply management positively impact this situation?

Options:

A.

Verify that recyclable packaging materials are properly coded for sorting

B.

Work with product development to ensure sustainable packaging is developed

C.

Include a notice with the product explaining that the packaging is recyclable

D.

Increase the amount of shrink-wrap packaging

Questions # 15:

A supply manager wishes to implement an enterprise resource planning (ERP) system. During which phase of the system development process should the supply manager communicate with end users to review their business environments?

Options:

A.

Testing

B.

Maintenance

C.

Design

D.

Analysis

Questions # 16:

A manufacturing firm is preparing a materials requirement plan for the next six weeks. The information is as follows:

Master Production Schedule

Week123456

Item A51015202530

Other Relevant Information

ItemItem's ParentItem's Lead TimeItem's Lot SizeItem's Current Inventory

ANone1 weekLFL20

BA2 weeks105

CB3 weeks205

How many levels does the product structure have in the bill of materials?

Options:

A.

1

B.

2

C.

0

D.

3

Questions # 17:

A supply manager is reviewing safety stock for a particular unit. The unit is small, Inexpensive, non-perishable, and easily stored, but is critical to the firm's manufacturing process. The following information is known about this unit:

Maximum lead time = 8 Days

Average lead time = 3 Days

Maximum daily usage = 6,000 Units

Average daily usage = 4,000 Units

What is the maximum safety stock that should be maintained for this unit?

Options:

A.

12,000

B.

10,000

C.

36,000

D.

48,000

Questions # 18:

A supplier with a previously good performance record has recently been shipping parts with a number of flaws, making them unusable for production. The firm’s supply manager would like to resolve these problems before taking more drastic measures. Which of the following actions should the supply manager take FIRST’

Options:

A.

Explore possible root causes, including changes in the supplier's production processes

B.

Ask engineering to review tolerances on non-critical specifications and relax them if possible

C.

Test the parts at an independent laboratory and notify the supplier of the results

D.

Re-work the parts in-house and bill the supplier for any costs incurred

Questions # 19:

A sourcing manager needs to outsource production in order to meet demand for a specific product. The internal production schedule and forecasted sales have been provided for the next nine months. Internal production follows a level schedule of 4,000 units per month and up to 7,000 units may be stored in inventory. There is no beginning inventory for January. During what month(s) will outsourced production be required to meet forecasted sales?

MonthJanFebMarAprMayJunJulAugSep

Unit Sales3,0003,0004,0001,0009,0005,0004,0003,0005,000

Options:

A.

June, July and September

B.

June only

C.

July only

D.

May, June and September

Questions # 20:

A scientific equipment company wants to encourage its key suppliers to participate in the firm's quality certification program. The process is detailed and time-consuming. Which of the following is likely to be the GREATEST benefit to the buying organization?

Options:

A.

Rationalized supply base

B.

Faster incoming inspections

C.

Reduced transaction time

D.

Lower total costs