Summer Certification Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code = getmirror

Pass the PECB ISO 21502 ISO-21502-Lead-Project-Manager Questions and answers with ExamsMirror

Practice at least 50% of the questions to maximize your chances of passing.
Exam ISO-21502-Lead-Project-Manager Premium Access

View all detail and faqs for the ISO-21502-Lead-Project-Manager exam


0 Students Passed

0% Average Score

0% Same Questions
Viewing page 2 out of 3 pages
Viewing questions 11-20 out of questions
Questions # 11:

According to ISO 21502, when is positive value created?

Options:

A.

When the investment of resources is similar to the benefits enabled by the project

B.

When the benefits enabled by the project exceed the investment of resources

C.

When the project produces deliverables, regardless of the resources allocated for its implementation

Questions # 12:

Which digital tools can be used to facilitate the collaboration of the project team?

Options:

A.

Agenda management, teleconferencing, document-sharing websites

B.

Planning software, digital collaboration, social media

C.

Both A and B

Questions # 13:

What are proposal requests?

Options:

A.

Requests from the contractor to the supplier to provide solutions for an intricate scope

B.

Requests when the solution is determined and when the price is the sole criterion for choosing the supplier

C.

Requests used to obtain supplier proposals when the buyer needs a proposed solution, approach, or offer for the required work

Questions # 14:

To whom does the project manager report?

Options:

A.

Only to organization’s top management

B.

Key stakeholders

C.

Project sponsor and project board

Questions # 15:

What is the purpose of the planning quality phase?

Options:

A.

To define the applicable standards and quality requirements regarding a project and its outcomes

B.

To ensure compliance with the determined quality requirements and applicable standards

C.

To determine if the requirements are being met and take actions to improve unsatisfactory performance

Questions # 16:

According to ISO 21502, why should the organizational strategy be used?

Options:

A.

To maximize the likelihood of success within the project environment and eliminate threats

B.

To identify, document, and evaluate opportunities, threats, weaknesses, and strengths, which can help inform future action

C.

To enable organizations to create tangible value instead of intangible value

Questions # 17:

According to PMBOK, what is the definition of Earned Value Analysis (EVA)?

Options:

A.

A method that utilizes a set of measures associated with scope, schedule, and cost to determine the cost and schedule performance of a project

B.

The amount of budget deficit or surplus at a given point in time, expressed as the difference between the earned value and the actual cost

C.

An earned value management measure that indicates how efficiently the work is being performed with regard to the budgeted cost of the work

Questions # 18:

Scenario:

Oakniture is a furniture manufacturer located in Bristol, England. It is known for its kitchen tables made out of different types of wood, such as chestnut, walnut, and oak. In early 2022, Lana, one of the senior researchers of the company, conducted a feasibility study to determine if there is a market for oak wood coffee tables, which indicated that the demand for oak wood coffee tables is relatively high. As such, Lana prepared a project brief and presented it to the top management of the company. The project brief included information on the project context and project objectives. After several discussions, the top management agreed that the project should be undertaken, but lastly, they asked Lana about the project duration. Lana claimed that the project duration cannot be determined and such information was not provided in the project brief; however, she added that the project duration will mainly depend on the competencies of the project team and on Oakniture’s suppliers of wood.

Following that, the top management initiated the project and assigned Tom, the operations director, as the project manager, and Lana as the project sponsor. To manage the project, they decided to use the guidelines of ISO 21502.

Initially, Tom defined the governance and management framework alone, and then he mobilized the team and assigned the roles and responsibilities to each team member. In addition, Tom and the project team identified the stakeholders and developed the project plan. To ensure effective management of each project phase, Tom used a work breakdown structure (WBS) to organize project activities. Tom presented the project activities in the WBS by linking task dependencies and showing project milestones. In addition, Tom calculated the duration of each work package by determining the early start and early finish dates. Regarding the relationship between work packages, Tom required the project team to perform tasks in the predetermined order, regardless of any resource shortages they might experience.

A week after the project implementation began, Tom collected and analyzed data regarding the progress of the project. To keep everyone up to date, he held a meeting with Lana and project stakeholders.

Question:

Scenario 4 states that Tom presented the project activities in the WBS by linking task dependencies and showing project milestones. Which WBS format did Tom use?

Options:

A.

Flowchart

B.

Gantt chart

C.

Gantt chart

Questions # 19:

Scenario:

Leute is a low-cost airline, headquartered in Wien, Austria. The company aims to offer passengers optimal options regarding its services and gain the lead role among other competitors in the airline industry. Recently, Leute experienced a major drop in revenue due to negative reviews from customers in various online platforms. To increase its profit and enhance customer satisfaction, the company decided to expand its in-flight services by offering entertainment, such as movies, audio books, and games, food for purchase in economy and full meals in premium cabins, and comforts, such as blankets and pillows. For the implementation of this project and future projects of the airline, the CEO of Leute, Michaele Wagner, decided to follow the guidelines of ISO 21502 on project management.

Initially, Allison, the project manager, created a short document in which she justified and summarized all project aspects, including: the nature and purpose of the project, the objectives of the project, key milestones of the project and the time needed to complete the project, and the audience that the project targets.

Afterward, Allison held a meeting with Michaele during which she presented this document and briefly explained each of its points. After a considerable amount of analysis and discussions, the project initiation was approved by Michaele. In addition, a team of eighteen members was authorized to start with the project activities.

While undertaking the project activities, Allison ensured that each work package takes longer than 8 hours, but less than 80 hours, so that they would be completed in 1 to 10 working days. In addition, during this phase, several changes were made in the predefined aspects of the project, which were approved by Nick Todd, the project sponsor. For instance, initially, the project delivery was set to be completed after six months. However, considering how the project was implemented and the time required for the completion of each phase, the deadline for the project completion was postponed for another two months. These changes were also reflected in the business case, which was updated accordingly.

A month after the project execution began, Allison conducted an earned value analysis to measure the progress of the project up to that stage. She measured how efficiently the work was being performed with regard to its budgeted cost, after which she concluded that it was going according to the plan. Moreover, she organized a meeting with relevant project stakeholders in order to communicate the progress report to them.

Question:

Based on scenario 3, Allison ensured that the size of each work package was longer than 8 hours, but less than 80 hours in order to complete them in 1 to 10 working days. What rule did Allison follow in this case?

Options:

A.

The 1/10 rule

B.

The 8/80 rule

C.

The reporting period rule

Questions # 20:

Scenario:

Oakniture is a furniture manufacturer located in Bristol, England. It is known for its kitchen tables made out of different types of wood, such as chestnut, walnut, and oak. In early 2022, Lana, one of the senior researchers of the company, conducted a feasibility study to determine if there is a market for oak wood coffee tables, which indicated that the demand for oak wood coffee tables is relatively high. As such, Lana prepared a project brief and presented it to the top management of the company. The project brief included information on the project context and project objectives. After several discussions, the top management agreed that the project should be undertaken, but lastly, they asked Lana about the project duration. Lana claimed that the project duration cannot be determined and such information was not provided in the project brief; however, she added that the project duration will mainly depend on the competencies of the project team and on Oakniture’s suppliers of wood.

Following that, the top management initiated the project and assigned Tom, the operations director, as the project manager, and Lana as the project sponsor. To manage the project, they decided to use the guidelines of ISO 21502.

Initially, Tom defined the governance and management framework alone, and then he mobilized the team and assigned the roles and responsibilities to each team member. In addition, Tom and the project team identified the stakeholders and developed the project plan. To ensure effective management of each project phase, Tom used a work breakdown structure (WBS) to organize project activities. Tom presented the project activities in the WBS by linking task dependencies and showing project milestones. In addition, Tom calculated the duration of each work package by determining the early start and early finish dates. Regarding the relationship between work packages, Tom required the project team to perform tasks in the predetermined order, regardless of any resource shortages they might experience.

A week after the project implementation began, Tom collected and analyzed data regarding the progress of the project. To keep everyone up to date, he held a meeting with Lana and project stakeholders.

Question:

According to scenario 4, Tom calculated the duration of each work package by determining the early start and early finish dates. Which of the following did Tom use in this case?

Options:

A.

Forward pass

B.

Backward pass

C.

Calculation float