Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code = getmirror

Pass the PMI Certification PMI-RMP Questions and answers with ExamsMirror

Practice at least 50% of the questions to maximize your chances of passing.
Exam PMI-RMP Premium Access

View all detail and faqs for the PMI-RMP exam


868 Students Passed

90% Average Score

97% Same Questions
Viewing page 4 out of 9 pages
Viewing questions 31-40 out of questions
Questions # 31:

The project team has correctly identified, assessed, and planned responses for a project's risks. The risk manager is required to prepare a quarterly report on the performance of managing the risks.

What are two options the risk manager should consult for the analysis? (Choose two.)

Options:

A.

Proximity dales for open risks

B.

Backlog of change orders to be submitted to client

C.

Risks that have materialized and the overall risk profile

D.

Number of schedule baseline changes approved

E.

Risks due to the number of claims submitted to the client

Questions # 32:

What is an example of legal and regulatory requirements and/or constraints when assessing a project environment for threats and opportunities?

Options:

A.

Organizational communication requirements

B.

Organizational standard policies, processes, and procedures

C.

Formal knowledge sharing and information sharing procedures

D.

Confidentiality of project information

Questions # 33:

A risk manager has to inform a project sponsor of the expected duration of an entire project. The project has three mam tasks, each with different probabilities of duration.

Which analytical tool should the risk manager use?

Options:

A.

Probability tree diagram

B.

Ishikawa diagram

C.

Decision tree analysis

D.

Monte Carlo simul-ation

Questions # 34:

A project is underway to implement a new customer support software. During testing, the risk manager discovers that the integration with the existing customer relationship management system is more complex than initially planned, potentially delaying the project. The risk manager needs to update project documents to reflect this new information.

Which steps should the risk manager consider when updating relevant project documents?

Options:

A.

Update the issue log with relevant information as the immediate concern for key stakeholders.

B.

Assume the delay will not affect the timeline and continue with the current scheduled activities.

C.

Update the project documents after the work has been completed and formally accepted.

D.

Assess the delay with the technical team, update the schedule and risk register, and inform stakeholders.

Questions # 35:

A risk manager is managing risks of a mission critical application. A subject matter expert (SME) asks the risk manager to treat every single risk identified as an extremely high priority.

What should the risk manager do?

Options:

A.

Ask the project sponsor if every risk in the risk register can have the same priority.

B.

Mark every identified risk as an extremely high priority and any future risks as a lower priority.

C.

Agree with the SME, treat every risk with equal priority, and inform all stakeholders.

D.

Perform a sensitivity analysis and determine the correct priority of every identified risk.

Questions # 36:

During a risk identification process in a construction project, the lack of space to install air conditioners is raised as a risk with high impact. Which is an example of an early risk trigger?

Options:

A.

A potential need to share the space with other machinery

B.

A different type of equipment received before installation

C.

A time delay during air conditioning installation activities

D.

A quality nonconformance issue raised during the inspection

Questions # 37:

A risk manager is tasked with establishing a risk management strategy for a multinational project with varying regulations and stakeholder priorities. The team is divided on how to approach risk management. Some suggest implementing rigid procedures to ensure consistency across regions, while others advocate for a flexible approach to adapt to the dynamic nature of local risks. Meanwhile, the sponsor emphasizes the need for a strategy that aligns with the overall project objectives.

What should the risk manager do?

Options:

A.

Implement a strict, standardized approach to ensure consistency across all regions.

B.

Develop a strategy combining structure with flexibility to address global and local uncertainties.

C.

Use organizational guidelines to create a strategy that prioritizes efficiency over adaptability.

D.

Adopt a fully flexible approach that allows teams to manage issues based on local context.

Questions # 38:

While performing risk identification exercises, the risk manager often encounters biases from the project team. How can the risk manager accurately identify what will trigger a risk?

Options:

A.

Remind the project team to keep an open mind

B.

Review the results with the project manager afterward

C.

Review published operational experience reports

D.

Use the mean answers provided by the project team 

Questions # 39:

During the project's lifecycle, project risk managers must monitor any risks and address risk responses. What does this level of monitoring consist of?

Options:

A.

Carry out the agreed risk response action should the risk occur.

B.

Provide a numerical estimate of the overall effect of risk on the objectives.

C.

Track identified risks and maintain the viability of response plans.

D.

Develop the overall risk management strategy for risk integration. 

Questions # 40:

A project manager managing a high-risk rating project was just informed that one of the key project resources has decided to leave the organization. The project manager asks the risk manager for their recommendations. The risk manager previously identified this as a risk and had created a transition plan to enable another resource to carry out the same duties. The risk manager was informed that by transitioning the responsibilities to the new resource, new risks to the completion dates of other project-related tasks appear.

What should the risk manager advise the project manager?

Options:

A.

Escalate the new risks immediately to the project stakeholders to ensure proper risk communication is in place.

B.

Address these secondary risks as per the risk management plan

C.

Apply a risk acceptance strategy to the new risks as there is no risk response plan.

D.

Update the risk management plan with the new probabily/impact and change the response.

Viewing page 4 out of 9 pages
Viewing questions 31-40 out of questions
TOP CODES

TOP CODES

Top selling exam codes in the certification world, popular, in demand and updated to help you pass on the first try.