Questions # 21:

The PMO VALUE RING has in its database:

Options:

A.

50 potential benefits and 40 potential functions for a PMO.

B.

26 potential benefits and 30 potential functions for a PMO.

C.

30 potential benefits and 26 potential functions for a PMO.

D.

15 potential benefits and 26 potential functions for a PMO.

Questions # 22:

Which factors should be considered during the selection of the PMO mix of functions?

Options:

A.

All answers are correct.

B.

The potential of the function in generating value over time.

C.

The probability of contribution of the function to meet the expectations of the stakeholders.

D.

If the function is appropriate for the strategy of the PMO and its organization.

Questions # 23:

What defines PMO maturity?

Options:

A.

The hierarchical positioning of the PMO In the organizational structure.

B.

The level of strategic competence in the PMO team.

C.

The level of sophistication with which each PMO function is performed

D.

The more strategic the PMO, the more mature it will be.

Questions # 24:

A PMO is undergoing an evaluation to understand the impact of its maturity level on organizational benefits. The team is considering how increased maturity influences aspects such as cost, team size, and stakeholder value. What is typically true about a PMO with greater maturity?

Options:

A.

The greater the maturity, the more strategic the PMO will become

B.

The greater the maturity, the larger the PMO team required to manage its functions

C.

The greater the maturity, the more functions the PMO is required to perform

D.

The greater the maturity, the higher the potential value generated for stakeholders

Questions # 25:

The greater the maturity of a PMO:

Options:

A.

The greater the number of functions performed by the PMO.

B.

The greater is the PMO team.

C.

The greater the PMO cost.

D.

The greater the value generated for the PMO stakeholders.

Questions # 26:

During a performance review, a PMO team discusses whether the success of the projects it oversees is a direct indicator of the PMO's success. Does the success of projects under the PMO mandate demonstrate the success of the PMO?

Options:

A.

Sometimes, depending on the specific functions the PMO is responsible for offering

B.

No, because the correlation between project success and PMO success is not relevant for a support area

C.

Yes, as successful projects enhance the perception of the value provided by the PMO

D.

Yes, because the PMO is always established to improve project performance

Questions # 27:

What defines a PMO function as strategic?

Options:

A.

Be directly related to business processes.

B.

Contribute to strategic planning.

C.

Be performed by the upper management.

D.

Be directly related to organizational strategy or upper management.