Questions # 11:

Which information should a Business Case for a P3O provide?

Options:

A.

Reasons why any form of P3O is needed

B.

Roles of the staff working in the P3O

C.

Processes to be implemented by the P3O

D.

Appointed Head of P3O

Questions # 12:

Which is a typical constraint which impacts on how a P3O is implemented?

Options:

A.

Pace of change must take into account current P3M3 maturity

B.

Quality, standardized data is needed

C.

P3O assurance services must be independent

D.

P3O governance must align with existing corporate governance

Questions # 13:

Which is an underlying success factor for a Temporary Office model?

Options:

A.

Consistent PPM training through approved training providers

B.

P3M3 maturity level of 3 or above

C.

Programmes or projects develop their own templates

D.

Programme or project culture does not exist

Questions # 14:

Which of the following statements about the return of internal resources to an operational role when closing a temporary Programme Office are true?

1. Feedback to the line manager should be given on performance

2. Staff members will be reluctant to return if they are to lose status

Options:

A.

Only 1 is true

B.

Only 2 is true

C.

Both 1 and 2 are true

D.

Neither 1 or 2 is true

Questions # 15:

Which of the following describe the governance responsibilities of a P3O model?

1. Provides the governance and control backbone for an organization's change initiatives

2. Provides a single source for all data relating to the organization's change initiatives

3. Implements rules for decision-making relating to programmes and projects

4. Makes decisions on behalf of the main board

Options:

A.

1,2,3

B.

1,2,4

C.

1,3,4

D.

2,3,4

Questions # 16:

Which of the following are key stakeholders in a temporary Project Office?

1. Organization Portfolio Office

2. Business as usual staff

3. Suppliers to the project

4. Project Board members

Options:

A.

1,2,3

B.

1,2,4

C.

1,3,4

D.

2,3,4

Questions # 17:

Which is NOT a functional role?

Options:

A.

Benefits and Value

B.

Information Management

C.

Project Officer

D.

Planning

Questions # 18:

What technique provides the benefit of checking the quality of the decision-support information being provided to the P3O?

Options:

A.

Gated reviews

B.

Business process swimlanes

C.

Capacity planning for resource management

D.

Management dashboards

Questions # 19:

Which P3O capability is MOST likely to result in being able to stop inappropriate programmes?

Options:

A.

Reduction in resource

B.

Ongoing alignment of programmes with strategic objectives and targets

C.

Reduction in overheads dealing with conflicting resources

D.

Increased ability to bundle related requests for change for programmes

Questions # 20:

What is defined as the decision-enabling and support business model for all business change within an organization?

Options:

A.

Programme

B.

P3O

C.

Project

D.

Portfolio

Viewing page 2 out of 3 pages
Viewing questions 11-20 out of questions