Questions # 1:

During stage 2, the design team is developing measures to minimize disruption to residents and local businesses. To build a relationship with this large external stakeholder group, the Sustainability Manager arranges a monthly newspaper article explaining the measures and inviting feedback.

Which PRINCE2 Project Management principle is MOST directly demonstrated, and why?

Options:

A.

Define roles, responsibilities and relationships, because the project is actively engaging and communicating with an external stakeholder group

B.

Define roles, responsibilities and relationships, because the Sustainability Manager must be the sole spokesperson for every project communication

C.

Tailor to suit the project, because every large project is required to communicate through a local newspaper

D.

Tailor to suit the project, because the Portfolio Director is personally accountable for preparing all stakeholder communications

Questions # 2:

As stage 3 approaches its end, the project manager seeks supplier-related advice from the CEO of BuildyBrick, acting in the senior supplier interest, about planning the testing and inspections in stage 4.

Under which ‘directing a project’ activity is this informal consultation provided?

Options:

A.

Authorize a stage or exception plan

B.

Give ongoing direction

C.

Authorize initiation

D.

Authorize the project

Questions # 3:

Near the end of stage 2, the supplier planned for the utilities and systems work becomes financially unstable and a replacement subcontractor is selected for stage 3. The project manager recommends that the replacement subcontractor’s account manager should represent the supplier interest as senior supplier.

During which ‘managing a stage boundary’ activity should this recommendation be developed?

Options:

A.

Update the project plan

B.

Prepare the next stage plan

C.

Evaluate the stage

D.

Request the next stage

Questions # 4:

At the end of the initiation stage, the Regeneration Manager submits the project plan and business case for review. The Portfolio Director releases funding for both stages 2 and 3 and instructs the project manager to provide only a progress report at the end of stage 2, without a project board decision before stage 3 begins.

Is this an appropriate application of the ‘manage by stages’ principle, and why?

Options:

A.

Yes, because the project manager is authorized to manage the project on a day-to-day basis within set tolerances throughout each stage, without requiring additional project board decisions

B.

Yes, because the Portfolio Director, as the commissioning authority, has the right to determine the reporting frequency and format that best suit portfolio-level oversight

C.

No, because it is the City Council, rather than the Portfolio Director, that should hold the authority to commit funding across multiple stages of the project

D.

No, because the project board must review the continued viability of the business case and authorize the next stage at each stage boundary, rather than approving multiple stages in advance

Questions # 5:

PROGRESS

Here are three actions related to the ‘progress’ practice for the LouisShopping project.

Which role (A–E) should be responsible for each action?

Choose only ONE role for each action. Each role can be used once, more than once, or not at all.

Options:

A.

Project executive

B.

Project manager

C.

Project assurance

D.

Team manager

E.

Project support

Action 1:

Assist the project manager in compiling the lessons report, including the recommendation that future projects allow more time for testing and inspections.

Action 2:

When delays to the floor installation cause the stage to be forecast beyond tolerance, submit an exception report to the project board for a decision.

Action 3:

Review the exception plan and decid

Questions # 6:

The City Council asks the portfolio office, independently of the LouisShopping project team, to provide confidence that the design and build will preserve the historic setting while incorporating the required technology.

Is this an appropriate application of the quality practice, and why?

Options:

A.

Yes, because the portfolio office should manage the project’s quality-control activities on behalf of the project manager

B.

Yes, because the business layer may use the portfolio office to perform independent quality-assurance activity on its behalf

C.

No, because assurance information may be provided to the project board and not to the business layer

D.

No, because a portfolio office may assess strategy but may not review the delivery of individual projects

Questions # 7:

RISK

Here are three items of information relating to the ‘risk’ practice.

In which management product (A–E) should each item be recorded?

Choose only ONE management product for each item of information. Each management product may be used once, more than once, or not at all.

Options:

A.

Risk register

B.

Issue register

C.

Quality management approach

D.

Issue report

E.

Risk management approach

Item 1:

A cracked pane has already been identified and replacement is planned for next week. The project manager records the separate uncertainty that the supplier may miss that future replacement date and delay subsequent work.

Item 2:

The agreed procedure states that the project board and project manager will review all open risks during every end stage assessment.

It

Questions # 8:

During initiation, the project executive asks the project manager to evaluate a credible business option that omits the underground car park. The project manager includes an investment appraisal of that option in the full business case, despite the main contractor’s objection.

Is this an appropriate application of the business case practice, and why?

Options:

A.

Yes, because developing the business case includes comparing credible business options to select the most appropriate investment

B.

Yes, because customer and supplier organizations must always maintain completely separate project business cases regardless of the given investment

C.

No, because a requirement in the initial scope may never be tested as part of an alternative option

D.

No, because anticipated parking income means that no alternative should be assessed

Questions # 9:

Before accepting the stage 2 design work package, the BuildyBrick team manager needs to determine how the design team will be organized and controlled and whether the work can be achieved within the stated constraints.

During which ‘managing product delivery’ activity should this be done?

Options:

A.

Notify work package completion

B.

Execute a work package

C.

Evaluate a work package

D.

Accept a work package

Questions # 10:

While selecting the project approach, the team identifies that a traditional delivery method and the proposed use of external suppliers could make the sustainability requirements harder to achieve. The risk is recorded in the project log for consideration during initiation.

Is this an appropriate application of ‘starting up a project’, and why?

Options:

A.

Yes, because the primary purpose of assessing the project approach at this stage is to clarify the prospective obligations of the project team and each external supplier when delivering the project products

B.

Yes, because the way the project work will be delivered directly influences how the management approaches are designed, and identifying risks early helps ensure the PID accurately reflects how sustainability will be managed

C.

No, because a risk that is classified as manageable does not pose a threat to overall project viability and should be deferred for consideration during the initiation stage when more detailed planning takes place using the traditional delivery method

D.

No, because any sustainability requirements that the project must satisfy should be captured as user quality expectations in the project product description, not as risks in the project log