Weekend Sale Special Limited Time 75% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code = drift75
Pass the PRINCE2 Certification PRINCE2-7-Practitioner Questions and answers with ExamsMirror
Exam PRINCE2-7-Practitioner Premium Access
View all detail and faqs for the PRINCE2-7-Practitioner exam
0 Students Passed
0% Average Score
0% Same Questions
During stage 2, the design team is developing measures to minimize disruption to residents and local businesses. To build a relationship with this large external stakeholder group, the Sustainability Manager arranges a monthly newspaper article explaining the measures and inviting feedback.
Which PRINCE2 Project Management principle is MOST directly demonstrated, and why?
As stage 3 approaches its end, the project manager seeks supplier-related advice from the CEO of BuildyBrick, acting in the senior supplier interest, about planning the testing and inspections in stage 4.
Under which ‘directing a project’ activity is this informal consultation provided?
Near the end of stage 2, the supplier planned for the utilities and systems work becomes financially unstable and a replacement subcontractor is selected for stage 3. The project manager recommends that the replacement subcontractor’s account manager should represent the supplier interest as senior supplier.
During which ‘managing a stage boundary’ activity should this recommendation be developed?
At the end of the initiation stage, the Regeneration Manager submits the project plan and business case for review. The Portfolio Director releases funding for both stages 2 and 3 and instructs the project manager to provide only a progress report at the end of stage 2, without a project board decision before stage 3 begins.
Is this an appropriate application of the ‘manage by stages’ principle, and why?
PROGRESS
Here are three actions related to the ‘progress’ practice for the LouisShopping project.
Which role (A–E) should be responsible for each action?
Choose only ONE role for each action. Each role can be used once, more than once, or not at all.
The City Council asks the portfolio office, independently of the LouisShopping project team, to provide confidence that the design and build will preserve the historic setting while incorporating the required technology.
Is this an appropriate application of the quality practice, and why?
RISK
Here are three items of information relating to the ‘risk’ practice.
In which management product (A–E) should each item be recorded?
Choose only ONE management product for each item of information. Each management product may be used once, more than once, or not at all.
During initiation, the project executive asks the project manager to evaluate a credible business option that omits the underground car park. The project manager includes an investment appraisal of that option in the full business case, despite the main contractor’s objection.
Is this an appropriate application of the business case practice, and why?
Before accepting the stage 2 design work package, the BuildyBrick team manager needs to determine how the design team will be organized and controlled and whether the work can be achieved within the stated constraints.
During which ‘managing product delivery’ activity should this be done?
While selecting the project approach, the team identifies that a traditional delivery method and the proposed use of external suppliers could make the sustainability requirements harder to achieve. The risk is recorded in the project log for consideration during initiation.
Is this an appropriate application of ‘starting up a project’, and why?
TOP CODES
Top selling exam codes in the certification world, popular, in demand and updated to help you pass on the first try.