Questions # 51:

What is the focus of Lean Thinking?

Options:

A.

Reducing delays

B.

Implementing objective measures of progress

C.

Ensuring respect for people and culture

D.

Moving to an iterative development process

Questions # 52:

What are two reasons Agile development is more beneficial than waterfall development? (Choose two.)

Options:

A.

It requires phase-gate approvals to ensure that everyone is moving together

B.

It increases productivity and employee engagement

C.

It allows businesses to deliver value to the market more quickly

D.

It relies on external provider dependencies

E.

It allows management to track project progress based on steering committees and metrics

Questions # 53:

Which of the following types of information is shown in a cumulative flow diagram?

Options:

A.

Team velocity

B.

Costs of producing artifacts

C.

Work that is in process across the whole team

D.

Time to complete a Feature by the rollup of Stories

Questions # 54:

What is one of the five basic Agile quality practices applicable to all Agile Teams?

Options:

A.

Using non-functional requirements

B.

Creating the Architectural Runway

C.

Decentralized decision-making

D.

Shift learning left

Questions # 55:

Which of the following categories addresses potential risks?

Options:

A.

Acquired

B.

Resolved

C.

Obtained

D.

Managed

Questions # 56:

Which statement defines the purpose of Iteration Planning?

Options:

A.

It is to analyze, approve, and ready Features for implementation

B.

It is to organize the work and define a realistic scope for the Iteration

C.

It is to break Stories into tasks that are achievable in the team's capacity

D.

It is to explore and implement program Epics and split them into Features to be further explored

Questions # 57:

The Scrum Master/Team Coach wants to establish a team's initial capacity. The team has two testers, three developers, one full-time Scrum Master/Team Coach, and a Product Owner split between two teams. What is their capacity before calculating for time off?

Options:

A.

48

B.

32

C.

52

D.

40

Questions # 58:

The CALMR approach to DevOps includes Automation, Lean flow, Measurement, and Recovery. What does the "C" represent?

Options:

A.

Cycle-time

B.

Cadence

C.

Continuous Integration

D.

Culture

Questions # 59:

Iteration planning, Iteration review, and backlog refinement are examples of which type of event

Options:

A.

PI event

B.

Team event

C.

Sync event

D.

Program event

Questions # 60:

Which of the following activities occurs during the Inspect and Adapt workshop?

Options:

A.

Refining the ART backlog

B.

A demo of the integrated system

C.

A retrospective of the Iteration

D.

Planning the next PI