Questions # 11:

What are two effective ways for a Scrum Team to ensure security concerns are satisfied? (choose the best two answers)

Options:

A.

Add security concerns to the Definition of Done.

B.

Delegate the work to the security department.

C.

Have the Scrum Team create Product Backlog items for each concern.

D.

Add a Sprint to specifically resolve all security concerns.

E.

Postpone the work until a specialist can perform a security audit and create a list of security-related Product Backlog items.

Questions # 12:

Who is responsible for the sizing of Product Backlog items?

(choose the best answer)

Options:

A.

The Product Owner with input from the Developers.

B.

The Scrum Master.

C.

The Developers, alone.

D.

The Developers after clarifying requirements with the Product Owner.

E.

The most senior people in the organization, including architects and subject matter

experts.

Questions # 13:

Which two things are appropriate for a Scrum Master to do, if the Scrum Team does not have

the tools and environment to completely finish each selected Product Backlog item?

(choose the best two answers)

Options:

A.

Coach the Scrum Team to improve its skills, tools and environment over time

and adjust the Definition of Done accordingly.

B.

Refocus the current Sprint on establishing the Scrum Team's environment

instead of delivering an Increment.

C.

Encourage the Product Owner to accept partially done Increments until the

situation improves.

D.

Have the Scrum Team establish a Definition of Done that is actually possible to

achieve given current circumstances.

E.

Declare the Scrum Team not ready for Scrum.

Questions # 14:

How much time must a Product Owner spend with the Developers?

(choose the best answer)

Options:

A.

Enough so that the Product Owner is confident the Increment will meet the intended value.

B.

40%, or more if the stakeholders agree.

C.

As much time as the Developers tell the Product Owner to be present.

D.

100%

Questions # 15:

True or False: Dependencies could influence how the Product Owner orders Product Backlog items.

Options:

A.

True

B.

False

Questions # 16:

A product's success is measured by:

(choose the best three answers)

Options:

A.

The impact on customer satisfaction.

B.

The impact on cost.

C.

The impact on my boss's mood.

D.

The delivery of upfront defined scope compared to the upfront planned time.

E.

The impact on my performance rating.

F.

The impact on revenue.

Questions # 17:

Which statement best describes Scrum?

(choose the best answer)

Options:

A.

A defined and predictive process that conforms to the principles of Scientific Management.

B.

A complete methodology that defines how to develop software.

C.

A framework to generate value through adaptive solutions for complex problems.

D.

A cookbook that defines best practices for software development.

Questions # 18:

Which three of the following are feedback loops in Scrum?

(choose the best three answers)

Options:

A.

Sprint Review.

B.

Refinement Meeting.

C.

Daily Scrum.

D.

Sprint Retrospective.

E.

Release Planning.

Questions # 19:

What is the responsibility of the Product Owner in crafting the Sprint Goal?

(choose the best answer)

Options:

A.

The Product Owner has no responsibility for the Sprint Goal. It is the sole

responsibility of the Developers.

B.

The Product Owner cannot attend Sprint Planning without having documented the

Sprint Goal in advance.

C.

The Product Owner should come to Sprint Planning with a business objective in mind and work with the Developers to craft the Sprint Goal.

D.

The Product Owner must work with stakeholders to set each Sprint's Goal.

E.

The Product Owner defines the scope for a Sprint and therefore also the Sprint Goal.

Questions # 20:

A Product Backlog is:

(choose the best three answers)

Options:

A.

An exhaustive list of upfront approved requirements to be implemented.

B.

Managed by the Product Owner.

C.

An inventory of things to be done for the Product.

D.

Ordered based on priority, value, dependencies, and risk.

E.

Only visible to the Product Owner and stakeholders.