Questions # 11:

In the approval path shown below, which Project Status will the Project be if rejected?

Options:

A.

Rejected

B.

Current

C.

Requested

Questions # 12:

Which project status will default the automatic Project Condition to “On Time”?

Options:

A.

Idea

B.

Planning

C.

On Hold

Questions # 13:

A user wants to add users to a proof based on who requested the project and the additional approvers listed in the request.

Which Workflow should the user choose?

Options:

A.

Automated

B.

Basic

C.

Manual

Questions # 14:

An assignee clicks Work On It for a task, and a new finish date appears on the task while the original planned finish stays the same.

What does this new date communicate to the project manager?

Options:

A.

It indicates that the assignee’s finish date is wrong and should be ignored.

B.

It indicates that the assignee’s finish date replaces the Planned Completion Date.

C.

It indicates the assignee’s own estimate of when they expect to finish the task, which can differ from the Planned Completion Date.

Questions # 15:

How is the primary assignee of a task determined?

Options:

A.

By the user on a task that has a primary job role.

B.

By the Home Team assigned to a task.

C.

By the user that is assigned first to a task.

Questions # 16:

The vice president of operations asks one of their project managers to create a Workfront report that automatically sums columns so that it is similar to a Microsoft Excel file. The project manager decides to use a matrix grouping to show the data, but one of the columns isn’t showing in the report.

What did the project manager forget to do?

Options:

A.

Summarize the columns.

B.

Update the grouping using text mode.

C.

Update the conditional formatting of the column.

Questions # 17:

A project manager compares the original schedule for a task to another set of dates that moved later after predecessors slipped and the assignee changed a completion commitment.

What do these later, system-calculated dates represent?

Options:

A.

They are Planned Dates that show the originally scheduled task dates.

B.

They are Projected Dates that show the current forecast for task start and finish.

C.

They are Milestone Path Dates that show when milestone tasks are expected to occur.

Questions # 18:

A project manager is updating a project in Workfront that is behind schedule.

Which action could be taken so that all tasks are completed by the requested completion date?

Options:

A.

Give all tasks a Task Constraint of “Must Start On”

B.

Reduce the durations of the tasks.

C.

Adjust all of the Planned Start Dates to the same day.

Questions # 19:

An executive wants to see the actual cost of projects within a selected portfolio, allowing for multiple reports with the option to select a specific portfolio, sorted in a descending order, so the most expensive projects appear on top. Which steps should be taken to create this report?

Options:

A.

Visit the Reports area and create a new Project report. Add a column for Actual Cost and sort the column in descending order. From the Reporting Settings dropdown, add a prompt for Portfolio Name.

B.

Visit the Reports area and create a new Project report. Group the results by Portfolio Name. Add a column for Actual Cost and summarize this column by SUM.

C.

Visit the Reports area and create a new Project report. Add a column for Actual Cost and sort the column in descending order. Group the results by Portfolio Name.

Questions # 20:

Executive stakeholders require both current metric reports and a weekly recap on a project.

How can both needs be met?

Options:

A.

Create a program-specific dashboard for the metrics and set up a weekly automated report to send.

B.

Create a program-specific dashboard for the metrics, then download a dashboard weekly to email to the stakeholder team.

C.

Create a program-specific dashboard for the metrics and add a calendar reminder for the team to review the report.