Questions # 21:

Which two statements are true about Groups and Teams? (Choose two.)

Options:

A.

A Team can be assigned to a task, but a Group cannot be assigned to a task.

B.

Objects can be shared with either a Group or a Team.

C.

A Group can be assigned to a task, but a Team cannot be assigned to a task.

D.

Work requests can be routed to either a Group or a Team.

Questions # 22:

To whom or what would a project owner assign a task so the task is visible in a Scrum or Kanban backlog?

Options:

A.

A user that has access to a burndown

B.

A job role labeled as Agile User

C.

A team marked as an agile team

Questions # 23:

A project manager needs to locate the fixed revenue and costs of a project. Where should the project manager look to find this information?

Options:

A.

Business Case

B.

Billing Records

C.

Project Details

Questions # 24:

The last 5 tasks in a project need to happen within 10 days of the end of the project.

Which Task Constraint should the project manager use to configure this timeline without setting specific dates?

Options:

A.

Start No Later Than

B.

Must Start On

C.

As Late As Possible

Questions # 25:

A task owner has Time Off logged in Workfront for all of next week. The owner has a task that is planned to start and is due while she is out.

What action should the task owner take?

Options:

A.

Set the task condition to At Risk.

B.

Update the Commit Date on the task.

C.

Work on the task and complete it in the given duration.

Questions # 26:

A project manager has been asked to create a report showing the planned completion date for all the project manager ' s projects. The report must show results in a calendar view and all entries should be purple. What steps should the project manager take to create this view?

Options:

A.

Visit the Reports page and create a new report. In the filter, update the project Owner ID field with the project manager’s name and set the Color ID field to purple. Add a column for Planned Completion Date and set the default view to “Calendar View.”

B.

Visit the Calendars page and create a new calendar. In the filter, update the date field to Planned Dates and update the Project Owner ID field with the project manager’s name. Set the color to purple.

C.

Visit the Reports page and create a new calendar. In the filter, update the Project Owner ID field with the project manager’s name and set the Color ID field to purple. Add a column for Planned Completion Date.

Questions # 27:

Two team members are assigned to a task that is expected to start this Tuesday based on the predecessor and the task constraint, but the Planned Start Date is showing as this Friday.

Why may this be the case?

Options:

A.

The primary task owner has time off logged in Workfront.

B.

The team needs to review the task before confirming the start date.

C.

The task duration and planned hours are set to begin on Friday.

Questions # 28:

A project sponsor has asked to see a summary of all projects that they are the sponsor of which were completed in the past year. The project sponsor wants to see the information grouped by the month the project was completed. What steps should the project manager take to create this view?

Options:

A.

Visit the Reports page and create a Project report. In the filter, update the actual completion date value to " past year " and update the Project Sponsor ID field to the project sponsor’s name. In the grouping tab, add a grouping for the actual completion date. In the Group Dates by field, select " month. "

B.

Visit the Reports page and create a Project Sponsor report. In the filter, update the actual completion date value with custom dates for the past year and update the Project Sponsor ID field to the project sponsor’s name. In the grouping tab, add a grouping for the planned completion date. In the Group Dates by field, select " month of year. "

C.

Visit the Dashboards page and create a Project report. In the filter, update the actual completion date value to " past year " and update the Project Sponsor ID field to the project sponsor’s name. In the grouping tab, add a grouping for the actual completion date. In the Group Dates by field, select " month of year. "