Questions # 11:

The BIM manager is working on a mixed-use project in which consultants are on different platforms and delivery timelines. The client requires COBie-compliant data handover and weekly coordination uploads.

What is the best approach to ensure project-specific BIM processes are effectively implemented from the outset?

Options:

A.

Facilitate a project-specific BIM kickoff session to align all contributors on workflows, deliverables, and data-handover protocols.

B.

Accept each firm’s standard BIM workflows and distribute them to the team to promote consistency across consultants.

C.

Focus on setting the Common Data Environment permissions first and allow teams to organize their workflows independently.

D.

Establish a baseline BIM Execution Plan, then adjust it incrementally based on coordination issues as they arise.

Questions # 12:

The project manager would like to verify Autodesk Forma folder permissions assigned to team members but is not familiar with cloud-sharing platforms to access this information.

How can the BIM manager generate the required information?

Options:

A.

Word document.

B.

Revit Show History report.

C.

Report exported from Autodesk Forma.

D.

Excel spreadsheet.

Questions # 13:

During an initial coordination meeting, the team agreed that the contractor will be able to mark up the latest model and sheets in Autodesk Forma every week.

Which two actions should the BIM Manager take to ensure this is implemented correctly? (Select two.)

Options:

A.

Email PDFs to the contractor every week.

B.

Update Publish Settings to include sheets.

C.

Create blank sheets for all disciplines.

D.

Enable Model Coordination.

E.

Schedule Publishes in Design Collaboration.

Questions # 14:

The BIM manager has finalized the BIM Execution Plan (BEP) for a multi-discipline educational facility project. Some consultants have already begun modelling, while others are onboarding late. A few external stakeholders are not listed in the original BEP distribution but will need access to coordinated models during design and preconstruction.

What two actions could be taken in order to manage distribution of updates? (Select two.)

Options:

A.

Update and reissue the BEP only to the consultants who have not yet started modelling to ensure they catch up to project standards.

B.

Formally distribute the BEP to all relevant parties as an addendum to the contract.

C.

Formally distribute the BEP to all relevant parties and confirm receipt to ensure alignment on roles, responsibilities, and agreed BIM processes.

D.

Upload the BEP in a shared Autodesk Forma Data Management folder to ensure version tracking and verify access to stakeholders.

E.

Wait until construction coordination begins before sharing the BEP with external stakeholders.

Questions # 15:

The BIM manager receives an external lighting CAD file to link into the Architectural model and realizes the link is not vertically or horizontally aligned.

What fix needs to happen to resolve this misalignment?

Options:

A.

The BIM manager needs to go to a 3D view and move the model to align with the architectural geometry.

B.

The Lighting team needs to fix its shared coordinates to match those of the Architectural model and reissue the file.

C.

The BIM manager needs to acquire the shared coordinates of the CAD file.

D.

The Lighting team needs to add gridlines so the BIM manager can align its CAD file to the architectural gridlines.

Questions # 16:

A design team is distributing models to a construction team’s coordinator, who reports that the various models are not aligned to each other when linked into the coordination environment.

What step should the design team’s lead BIM manager take to resolve the positioning issue?

Options:

A.

Reset coordinates and advise the coordinator to link all models by Internal Origin to Internal Origin.

B.

Publish coordinates from the Main Model out to all linked consumed consultant files.

C.

Report coordinates to provide the coordinator with the desired positioning of each model for them to reposition.

D.

Advise consultants to acquire coordinates from the primary design team’s model and resubmit updated models.

Questions # 17:

During a model health check, a BIM manager notices that an international airport project’s models are 1 GB each. The team has not mentioned any issues, but they did miss a recent 50% Construction Documents deadline.

What should the BIM manager do?

Options:

A.

Create a separate model for sheets and ask the team to audit and compact the models every day.

B.

Proceed to check another project’s model health since the team has not mentioned any issues.

C.

Coordinate with the project team to purge the model, remove unused views, and address warnings.

D.

Assign multiple BIM managers to the project and take one week to clear every warning.