Weekend Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code = simple70

Pass the BICSI RCDD Certification RCDDv14 Questions and answers with ExamsMirror

Practice at least 50% of the questions to maximize your chances of passing.
Exam RCDDv14 Premium Access

View all detail and faqs for the RCDDv14 exam


347 Students Passed

85% Average Score

92% Same Questions
Viewing page 1 out of 9 pages
Viewing questions 1-10 out of questions
Questions # 1:

An organization requests that a junior project manager, with no previous experience or training in the industry take over a complex program component. The program component involves senior subject matter experts and has dependencies with other large projects to deliver key benefits to the organization.

How should the junior project manager respond to this request?

Options:

A.

Accept the assignment, identify the skill gaps and request training

B.

Reject the assignment, because of the ethical requirement not to accept work for which the project manager is not qualified

C.

Accept the assignment as a challenge and an opportunity to acquire new skills and seek advice from a senior project manager

D.

Reject the assignment because of fear of failure and resulting negative career impact

Questions # 2:

After taking over a program, a program manager reviews the program's status and discovers that stakeholders do not know how the program is performing in relation to schedule and costs The program manager establishes earned value (EV) metrics and determines that the program has a budget of USS2.1 million, is three months into a nine-month timeline, and the planned value (PV) at the three-month point should be US$320,000. The program has spent US$350,000 and the EV is US$340,000

Based on this information, the program manager determines which of the following?

Options:

A.

The schedule is US%30.000 under budget

B.

The cost is US$20.0O0 under budget

C.

The schedule is US$10.000 over budget

D.

The cost is USS20.000 over budget

Questions # 3:

A large automaker begins a program to create the next-generation car. As the program team is composed, key stakeholders are identified

Key stakeholders for the program should include which of the following?

Options:

A.

Potential customers, government regulatory agencies, and competitors

B.

Project management office (PMO), third-party contractors, and agents

C.

Local car dealers, factory workers, and corporate officers

D.

Vice president of logistics, potential customers, and corporate executives

Questions # 4:

A regional finance program is impacted by a new currency regulation issued by a country in the region. The new regulation requires changes to the financial statements of that country's branches by the end of the fiscal year Failing to comply with the regulation may result in fines and/or closure of the branches. A branch general manager immediately meets with the program manager to select and secure a local fiscal expert to support the regulation as these types of resources are in high demand. There is a high risk that the changes will not be completed on time if the resource is not secured

What should the program manager do to address the risk?

Options:

A.

Build a coalition with local companies that can influence the government to renegotiate the imposed deadline

B.

Create fine and closure scenarios to assess the impact on the program and create a contingency plan

C.

Generate a delivery incentive contract with the selected fiscal expert to ensure on-time delivery of the revised financial statements

D.

Assess the risk incorporate it in the program's risk management plan and meet with the steering committee

Questions # 5:

Which two of the following documents MUST be submitted by the communication's project contractor for review and approval? {Select two options.)

Options:

A.

Test reports

B.

Shop drawings

C.

Cost summary

D.

Site survey

E.

Request for information (RFI)

Questions # 6:

Several issues are identified on one component project in a program During a meeting with that component's project manager, the program manager offers several suggested resolutions Two weeks later, they meet again to review progress The project manager had reviewed the issues and suggested resolutions, but delayed a decision. This two-week delay in taking action caused delays in the project schedule

What should the program manager do?

Options:

A.

Join project-level issue resolution meetings to accelerate the decision-making process.

B.

Initiate discussions with the program governance board about assigning a more experienced project manager to the project

C.

Emphasize that the project manager needs to address the issues and follow up at the next scheduled meeting

D.

Develop an immediate corrective action plan with the project manager and coach them on decision-making responsibilities

Questions # 7:

A program manager takes over a global program from another program manager. Upon arriving on-site, the program manager immediately sees that stakeholders are upset because of a lack of updates and communications about the program.

What should the program manager do first?

Options:

A.

Review the program governance plan and communication log

B.

Review the program communications management plan and stakeholder register

C.

Review the stakeholder engagement plan and stakeholder matrix

D.

Notify the executive sponsor and update the program issue tog

Questions # 8:

Which two of the following are ADVANTAGES of underground conduit systems? (Select two options.)

Options:

A.

Provide additional physical cable protection

B.

Not adaptable for future facility placement or removal without disturbing the property

C.

Economical over a long life

D.

Require more installation time than aerial or direct-buried installations

E.

Route planning is not as critical as aerial or direct-burial

Questions # 9:

A program with objectives trial impact a large segment of the population receives negative commentary from organizations representing the public interest What action should the program manager take first?

Options:

A.

Rework the stakeholder engagement plan to foster better relationships with the affected stakeholder groups

B.

Review the stakeholder register to determine the ability of the affected stakeholder group(s) to affect program outcomes

C.

Assess the risk of sustained negative media coverage

D.

Discuss the issues with the governance board to determine next steps

Questions # 10:

The program manager wants to ensure that a program contributes to shareholder value. The program manager should verify alignment with which of the following?

Options:

A.

Program charter

B.

Organizational structures and policies

C.

Organizational strategic objectives

D.

Program governance plan

Viewing page 1 out of 9 pages
Viewing questions 1-10 out of questions
TOP CODES

TOP CODES

Top selling exam codes in the certification world, popular, in demand and updated to help you pass on the first try.