Questions # 11:

Which technology would be BEST to notify facility occupants during an emergency?

Options:

A.

Company's social media profile.

B.

Emergency notification system.

C.

E-mail system.

D.

Incident management system.

Questions # 12:

As the Facility Manager, you secured 5,500 square feet of Class A office space on a multi-tenant floor to support a two-year business initiative. To minimize capital investment, the space will be used with pre-existing furnishings, fixtures, and equipment. However, before you can move people into this space, you will need a certificate of occupancy. What system must be examined to obtain a certificate of occupancy?

Options:

A.

Life safety system

B.

Potable water system

C.

Network connections

D.

Telephone system

Questions # 13:

During regular preventive maintenance activities, you notice green algae and scaling on the interior walls of the cooling tower. What action should you take to resolve the concerns?

Options:

A.

Shutdown the tower, allow surfaces to dry, and scrape biological growth from interior walls before returning the tower to operation.

B.

Test the cooling tower water, adjust the frequency of chemical balancing, and flush if needed.

C.

Perform a building occupant health survey to determine any adverse effects, and then adjust the injection levels of balancing chemicals.

D.

Drain the tower and then complete a fresh-water flush using warm water, and add new balancing chemicals.

Questions # 14:

To satisfy the needs of one of its largest customers, your company is opening a new facility about 1240 miles/2000 kilometers away from the corporate offices. Initially, the new operation will only support one customer. However, the company expects more customers will be added in the next three to five years. The plan is that the corporate office will support operations in the new facility. What is the best way to manage the facility requirements of this new operation?

Options:

A.

Use a temporary agency for facility services and manage everything from the corporate office.

B.

Hire a permanent staff of facility employees for the new operation.

C.

Contract with an outsource company to provide facility management services for the new operation.

D.

Relocate some existing facility employees to the new operation.

Questions # 15:

You are a Facility Manager overseeing a proposed renovation of a floor to meet the needs of the business. What step should be taken first?

Options:

A.

Conduct space programming analysis.

B.

Perform a gap analysis.

C.

Engage an architect for scenario alternatives.

D.

Undergo a feasibility study.

Questions # 16:

What is the benefit of documenting lessons learned for projects?

Options:

A.

Provides inputs to the project issue log

B.

Summarizes the effect of decisions made on a project and serves as a guide for what to repeat and what to avoid in future projects

C.

Provides key inputs to create the project charter, develop the project management plan, and finalize the stakeholder register

Questions # 17:

After completing a renovation of a wing of an older building, what actions will a Facility Manager do prior to occupancy to remove pollutants from the newly installed finishes?

Options:

A.

Adjust the HVAC.

B.

Run the building's air conditioning for a legally required period.

C.

Bring 100% fresh air into the area.

Questions # 18:

You are the Facility Manager leading a project to integrate two office groups. You will need a unifying message that guides your communications and decision-making when working with a variety of consultants, senior management, and the affected groups. What is your unifying message?

Options:

A.

How the project benefits and contributes to the success of the organization.

B.

The needs of the executives who own the project and how they want things done.

C.

How long the project is expected to take, what it will cost, and key parties involved.

D.

Who will be impacted by the project and how their work lives will be improved.

Questions # 19:

What approach best promotes indoor environmental quality and health?

Options:

A.

The maintenance and monitoring of acceptable levels of ambiance, safety, lighting, and environmental wellness.

B.

The strategies and systems used to provide occupants with a healthy, productive, comfortable, and safe workplace.

C.

The measurement and monitoring of hazardous conditions that pose threats to health, the environment, and the quality of life.

Questions # 20:

Various workers in a facility are complaining about neck, shoulder, and back pain. The facility manager decides to execute an ergonomic audit. What is the primary purpose of an ergonomic audit?

Options:

A.

Identify new requirements for ergonomic equipment.

B.

Improve worker productivity.

C.

Identify existing problems and prevent future injuries.

D.

Determine a training program for the workers.

Viewing page 2 out of 8 pages
Viewing questions 11-20 out of questions