Questions # 151:

You are the business analyst for your organization and you're creating a business analysis communication management plan. In your plan, you want to address the different locales and culture and the communication needs that may affect the business analysis approach. Which one of the following elements should not be included in the cultural analysis of the plan?

Options:

A.

Relationship to task completion

B.

Relationship to authority

C.

Relationship to religion

D.

Relationship to time

Questions # 152:

You have been assigned as the Project Manager for a new project that involves the development of a new interface for your existing time management system. You would like to plan the communications that need to be made during the project lifecycle. Which of the following would be a critical tool/technique to help in your communications planning?

Options:

A.

RAM Chart

B.

Affinity Diagram

C.

Stakeholder Analysis

D.

Text-Oriented Chart

Questions # 153:

Which of the following defines all of the required work to satisfy the requirements of the project?

Options:

A.

Project scope

B.

Requirements envisioning

C.

Requirements foundation

D.

Product scope

Questions # 154:

A project to implement shared registration procedures across multiple jurisdictions has stalled several times. The new business analyst (BA) assigned to the project used a collaborative game to elicit requirements. What effect was the BA attempting to achieve?

Options:

A.

Minimal variance from planned effort

B.

Close alignment with corporate values

C.

Stimulate teamwork in a fun situation

D.

High confidence in conclusions

Questions # 155:

You are a business analyst for your organization. Your current business analysis endeavor includes working with stakeholders located in offices around the world. Because these stakeholders are dispersed, what is likely to increase in this endeavor as opposed to a collocated group of stakeholders?

Options:

A.

Costs

B.

Face-to-face meetings

C.

Communication needs

D.

Risks

Questions # 156:

A business analyst is meeting with the customer of the project. The customer tells the business analyst that she can only allow the budget of $575,000 for the project. This budget is best described as what type of constraint?

Options:

A.

Technical constraint

B.

Verified constraint

C.

Financial constraint

D.

Business constraint

Questions # 157:

A change is desired in a project after the requirements are signed off and after technical design has started. The stakeholders want an additional product to be developed as part of the project. What tool can be used by the business analyst (BA) to assess the impact of the change?

Options:

A.

Backlog management

B.

Balanced scorecard

C.

Concept modeling

D.

Requirements architecture

Questions # 158:

A business analyst (BA) has structured information so it is easy to find, does not conflict with other information, and is not duplicated unnecessarily. Which additional factor does the BA need to take into account when deciding how to structure the information?

Options:

A.

The number of stakeholders to be consulted

B.

The governance and engagement approach to be used

C.

The level of experience with the repository tool

D.

The size and complexity of the change

Questions # 159:

A business analyst (BA) is facilitating a meeting with subject matter experts (SMEs) in which the SMEs are answering questions about the major business processes and associated activities the business performs. The BA will create a deliverable from this discussion that will assist in defining scope. What technique is the BA using?

Options:

A.

Decision modeling

B.

Mind mapping

C.

SWOT analysis

D.

Functional decomposition

Questions # 160:

A business analyst (BA) is given an additional requirement near the end of the development phase that needs to be incorporated into the system as part of the same release. In this situation, the first activity the BA performs to understand the effect of the proposed change is to:

Options:

A.

Check with the project manager for timeline and budget metrics.

B.

Determine whether stakeholders are available for further elicitation.

C.

Determine whether the additional requirement is traceable to a need.

D.

Consult with the technical team for technical feasibility.

Questions # 161:

A business analyst (BA) has identified the impacts and resolution for a proposed change. Based on the Responsible, Accountable, Consulted, Informed (RACI) matrix, who must approve the change before it is implemented?

Options:

A.

Business sponsor

B.

Subject matter expert

C.

Project manager

D.

System architect

Questions # 162:

The director of a furniture store manages a group of skilled carpenters who make furniture from locally available materials. The director decides to automate its inventory processes so that the carpenters can place orders for raw materials themselves. A business analyst (BA) is engaged to define the requirements and propose options for commercial off-the-shelf (COTS) inventory management solutions. After meeting with the director, the BA needs to schedule a workshop with the carpenters to:

Options:

A.

Investigate whether automation is a constraint for the end users.

B.

Demonstrate some of the proposed solutions to end users.

C.

Convey the benefits of the automation to the end users.

D.

Present the proposed future state to the end users.

Questions # 163:

During a senior management meeting about a project at the requirements analysis stage, a business analyst (BA) stated that there were a number of workarounds associated with the current application. The Chief Information Officer (CIO) was looking for ways to improve the situation, and the BA suggests a solution. Which of the following can the BA suggest that the organization consider to increase efficiencies?

Options:

A.

Strategic realignment

B.

Capability assessment

C.

Project abandonment

D.

Process improvement

Questions # 164:

During planning, elicitation, and sign-off of requirements, the stakeholders felt that their opinions were not heard and information was not frequently shared. What major competency was lacking in this process?

Options:

A.

Communication

B.

Information

C.

Collaboration

D.

Trustworthiness

Questions # 165:

A business analyst (BA) has elicited non-functional information for a system's replacement. In reviewing the elicitation results, the BA finds the number of concurrent users is a large portion of the target user group, which seems high. How should the BA proceed?

Options:

A.

Document the elicitation results in the solution requirements specification, then seek verification and validation in a requirements review

B.

Observe a user performing the task to determine the length of time to complete the task

C.

Conduct additional stakeholder analysis to determine whether any additional user groups were overlooked

D.

Confirm elicitation results by researching the actual concurrent users on the existing system and review findings with stakeholders