Questions # 226:

A nurse working a second overtime shift accidentally administered an oral medication via the patient's IV line. The facility reported this to the accrediting body as a sentinel event. Which of the following is the best solution to prevent this error from happening again?

Options:

A.

Label syringes “For Oral Use Only” if the medication is to be given orally.

B.

Educate staff on the potential consequences of device misconnections.

C.

Decrease the amount of overtime hours worked by hospital nurses.

D.

Purchase products with design features to prevent misconnections.

Questions # 227:

Which of the following process improvement training methods would be effective to support a continuous survey readiness program?

Options:

A.

Written assignments

B.

Aligning policies with accreditation standards

C.

Staff knowledge assessment with education

D.

Formal classroom training

Questions # 228:

A performance Improvement team has been meeting to examine delays in getting admissions from theemergency room to the nursing units. After six months of collecting data, the upper control limit was ISO minutes, and the lower control limit was 60 minutes. The next month's data shows a time of 155 minutes. The team should understand that this represents what type of variation?

Options:

A.

standard

B.

random

C.

common cause

D.

special cause

Questions # 229:

The following data are known:

Which ofthe following accurately describes this chart?

Options:

A.

The lower control limits were the same in Report Time A and B.

B.

The mode was 0.7517 In Report Time B.

C.

There was one outlier in Report Time A.

D.

There were no special cause variations.

Questions # 230:

Which of the following demonstrates interrater reliability and construct validity for an instrument designed to capture data for a publicly reported measure set?

Option

Interrater Reliability

Construct Validity

A

Two or more abstractors enter identical responses when reviewing the same record.

The tool measures the quality of care which the measure developers intended to measure.

B

Trained data collectors can reliably predict results after reviewing a random sample of records.

The tool includes data elements that measure the aspects of quality which are important to the public.

C

Concordance between process and outcome measures can be accurately estimated by the measure developers.

The instrument enables statistically valid inferences to be drawn about the quality of care delivered.

D

The design of the instrument minimizes falsified answers and other data entry errors.

The instrument captures variations in care processes across the population.

Options:

A.

A

B.

B

C.

C

D.

D

Questions # 231:

An organization decides to transition from a departmental quality assurance model to a multidisciplinary quality improvement model. The first step to ensure successful change is to:

Options:

A.

Demonstrate leadership commitment to the change.

B.

Evaluate the staff members’ readiness for change.

C.

Communicate the change throughout the organization.

D.

Assess the current quality model.

Questions # 232:

The staff in the outpatient department complete the morning schedule at varied times. There are multiple factors in the variation such as number of patients, complexity of the cases, and the number of cancellations. To identify common-cause variation affecting the completion of the morning schedules, what type of chart should be utilized?

Options:

A.

pie chart

B.

bar chart

C.

line graph

D.

control chart

Questions # 233:

An organization is implementing a palliative care unit. As part of the planning and implementation processes, the board authorizes the following:

• Learning visits with existing programs to obtain information about best practices

• Formal training of all staff assigned to the unit in the principles of palliative care

• The development of a balanced scorecard to monitor program performance

The actions of the board best illustrate

Options:

A.

High-level strategic planning

B.

A board’s need to manage patient care

C.

A commitment to quality

D.

The importance of competence and training

Questions # 234:

A researcher decides to look at every fourth patient admitted each day and record if the IV is properly labeled, starting with a randomly selected patient. This is known as which of the following types of random selection?

Options:

A.

Simple

B.

Convenience

C.

Systematic

D.

Stratified

Questions # 235:

A quality professional was asked to assist with strategic planning. Which of the following should have the primary impact on the quality and performance improvement goals?

Options:

A.

report of major competitors ‘performance

B.

findings from a staff needs assessment

C.

financial statement of the organization

D.

results of gap analysis

Questions # 236:

According to the Institute of Medicine’s (IOM) report, Crossing the Quality Chasm, which of the following is identified as one of the six aims for improvement?

Options:

A.

Low costs

B.

Population-centered

C.

Effective

D.

Coordinated

Questions # 237:

There has been an increase in readmissions and chart reviews show that it is related to medication non-adherence post-discharge. To improve medication adherence, the quality professional recommends staff:

Options:

A.

Use teach-back to establish an understanding of the patient’s medication plan.

B.

Evaluate patient barriers to obtaining medications.

C.

Complete medication reconciliation prior to discharge.

D.

Provide printed medication information for the patient to take home.

Questions # 238:

The primary objective of the project charter is to

Options:

A.

Track progress of the improvement project

B.

Evaluate the productivity of the involved departments

C.

Establish the purpose of the project

D.

Document the project expenses

Questions # 239:

Supporting patients through longitudinal care plans is the guiding principle of:

Options:

A.

Emerging healthcare models.

B.

Team-based care.

C.

Care coordination.

D.

Patient engagement.

Questions # 240:

The strategic plan for an organization calls for expansion of information technology. The following information is available:

If equal weight is given to each consideration, which of the following options should be the primary choice?

Options:

A.

Option A

B.

Option B

C.

Option C

D.

Option D