Questions # 41:

How should a minor quality control failure during the creation of a product be addressed initially?

Options:

A.

By escalating the issue to the project manager

B.

By performing an independent review of the product

C.

By revisiting the development and test activities

D.

By discussing with the chief product owner

Questions # 42:

Which workshop revisits and refines personas and any evolving user needs?

Options:

A.

Team retrospective workshop

B.

Project kickoff workshop

C.

Release planning workshop

D.

Agile enablement workshop

Questions # 43:

Which is a benefit of the Lean Startup approach to releasing a product?

Options:

A.

It provide a technique to reduce the testing of a product before release

B.

It enables the release plans to be synchronized with the PRINCE2 plans

C.

It reduces the number of people needed to manage a release of a product

D.

It provides quick feedback that can be responded to at the earliest opportunity

Questions # 44:

Which Agile approach is an iterative and timeboxed approach to product delivery?

Options:

A.

Scrum

B.

Kanban

C.

Agilometer

D.

Lean

Questions # 45:

How is the ‘learn from experience’ principle applied in an agile context?

Options:

A.

By ensuring control through lots of short stages during innovative projects

B.

By using the Agilometer to assess risks associated with the agile way of working

C.

By continual customer involvement to obtain feedback during the project

D.

By prioritizing quality criteria to focus the project on the delivery of value

Questions # 46:

Which PRINCE2 principle should be followed in order to engage the business, user and supplier stakeholder interests?

Options:

A.

Defined roles and responsibilities

B.

Continued business justification

C.

Learn from experience

D.

Tailor to suit the project

Questions # 47:

Which is an advantage of frequent releases?

Options:

A.

Releases can be used to replace management stages

B.

A ‘one-team’ culture in the project team is encouraged

C.

Configuration management becomes less important

D.

The delivery team becomes more experienced at product handover

Questions # 48:

Which is an advantage of using the PRINCE2 Agile behavior ‘collaboration’?

Options:

A.

It ensures that there are no surprises

B.

It allows people to provide cover for one another

C.

It uses experimentation to expand requirements

D.

It uses learning to help improve products

Questions # 49:

Which practice supports identification and assessment of uncertainties?

Options:

A.

Risk

B.

Plans

C.

Quality

D.

Business case

Questions # 50:

Which statement about the ‘keep teams stable’ target is CORRECT?

Options:

A.

It applies primarily to the long term, such as a project or a program

B.

It is the primary reason why the tolerance for cost is set to zero

C.

It prevents compromising the overall quality level of the product

D.

It results in the early delivery of a minimum viable product