Questions # 1:

The scheduler should assign work plans for the crew to execute what percentage of the forecasted hours?

Options:

A.

100% to fill all available forecasted hours

B.

More than 100% in case some jobs do not take as long

C.

Less than 100% to allow for emergencies or breaks

D.

It does not matter how much is scheduled

Questions # 2:

Why may two different materials, both with the same surface temperature, appear to havedifferent temperatures when viewed with a thermal imager?

Options:

A.

They have different convective coefficients.

B.

They have different emissivities.

C.

They have different thermal capacities.

D.

They have different conductivities.

Questions # 3:

The maintenance manager of a bearing manufacturer has asked you to calculate the reorder point of a spare part item. She has provided you with the following information to facilitate your calculations. The cost of the spare parties$100. The cost of earning inventory is 20% of the cost of the part. The cost of placing an order is$40 for which the annual demand is 100,000 units. The average tad-time for replenishment is two weeks and the buffer stock of 500 units S desired and the average inventory is 100 units per week. What is the reorder point in units for this spare part?

Options:

A.

350 units

B.

600 units

C.

700 units

D.

707 units

E.

1200 units

Questions # 4:

The Maintainability of a machine may be measured by:

Options:

A.

Life Cycle Cost.

B.

Machine Maintenance Cost.

C.

Failure Rate.

D.

Mean Time To Repair (MTTR).

Questions # 5:

Which answer is not one of the steps in performing an RCA (Root Cause Analysis)?

Options:

A.

Track the recommended solutions to ensure effectiveness.

B.

Develop solutions and recommendations.

C.

Identify possible mitigating factors.

D.

Define the problem or the failure.

Questions # 6:

One way to catch up on back log hours in PM's is to hire outside contractors to complete backlog work tasks. What should a reliability engineer do when making this decision?

Options:

A.

assure contractor personnel have many years of experience

B.

assure contractors have training programs and documentation from other plant operations

C.

assure contractors have proper safety paperwork on file

D.

assure contractors have been trained in work tasks

Questions # 7:

Maintainability is defined as:

Options:

A.

a characteristic of a system or product design .that pertains to the ease, accuracy, safety and economy in the performance of maintenance functions ^

B.

a characteristic that pertains to the amount of time the machinery/equipment will be available when needed

C.

a characteristic that pertains to the efficient conversion of labor, raw material and energy into an on-specification product where the ratio of output to input is optimal

D.

the probability that an item will carry out its stated function adequately for the time intervalwhen operating according to the design function

Questions # 8:

What is the best way for a Maintenance and Reliability Program to use process parameters?

Options:

A.

Justify replacement equipment purchases

B.

Assist in the explanation of failures

C.

Assign detects to equipment and systems

D.

Correlate to changes in equipment condition

Questions # 9:

What would dictate the basicminimum skill requirements for new Maintenance and Reliability employees?

Options:

A.

The skills available in the general workforce

B.

The current level of plant (facility) technology

C.

The content of the apprenticeship program

D.

The educational demographics of the region

Questions # 10:

Which one of the following metrics definitions is not accurate?

Options:

A.

Work Order Cycle Time - average number of hours jobs are planned in advance of execution

B.

Mean TimeTo Repair (MTIR) how long it takes to fix broken equipment

C.

Estimated Asset Replacement Value per Mechanic - how much equipment value is maintained by each mechanic

D.

% Planned Work - the amount of completed work that was planned ahead of time