Questions # 71:

A project manager has been informed that the delivery of required IT equipment will be delayed. Which of the following is the FIRST step the project manager should take?

Options:

A.

Make an impact assessment.

B.

Prepare a new purchase order.

C.

Select a new vendor.

D.

Create a risk register.

Questions # 72:

A project team member wrote a user guide over the past ten days. Given the following scatter diagram.

Which erf the following can be formally conducted?

Options:

A.

The team member prioritized other tasks over the completion of this task

B.

The learn member had performance issues over time.

C.

There is a negative correlation with 6me and output

D.

This is a display of units of outstanding work to predict completion

Questions # 73:

A client made a change request. Implementing the change will cause a delay in the project and a budget overrun. Which of the following should the project manager do first?

Options:

A.

Update the WBS.

B.

Escalate to the CCB.

C.

Accept the change.

D.

Implement the change.

Questions # 74:

Which of the following tasks should the project manager complete first when validating deliverables?

Options:

A.

Assess the documentation.

B.

Obtain stakeholder feedback.

C.

Review the project objectives.

D.

Mitigate risks.

Questions # 75:

A company is designing a new ERP system. The SOW includes modules for different departments. During a meeting, a stakeholder requests an additional feature. Which of the following action should the project manager take next?

Options:

A.

Document the change request in the change log.

B.

Communicate the change request to stakeholders.

C.

Determine the decision makers for the change request.

D.

Validate the change request.

Questions # 76:

A project misses a deadline. The project manager creates the following diagram:

Execution: The change control process was not followed. The customer added requests for previously unrequested features. The team developed unnecessary features.

Requirements: The customer did not provide all requirements during the initiation phase.

Question # 76

Which of the following is most likely the root cause of the delay?

Options:

A.

Team conflicts

B.

Unvalidated deliverables

C.

Scope creep

D.

Gold plating

Questions # 77:

Which of the following would most likely take place when a team reviews the backlog and presents the status of each task?

Options:

A.

Sprint retrospective

B.

Sprint review

C.

Sprint planning

D.

Daily Scrum

Questions # 78:

Which of the following is a quality assurance tool?

Options:

A.

Defining project goals

B.

Identifying the root cause analysis

C.

Assessing employee efficiency

D.

Assessing skill gaps

Questions # 79:

A project manager prefers to have immediate contact with team members because it allows for faster response times and more interactive discussions. Which of the following communication methods should the project manager use?

Options:

A.

Synchronous

B.

Informal

C.

Asynchronous

D.

Formal

Questions # 80:

Which of the following is the best alternative to allow multiple users to edit a project plan in real time?

Options:

A.

Send the file through email as an attachment

B.

Share access to the file on a wiki knowledge base.

C.

Access the file through an online application.

D.

Schedule an in-person meeting to review the plan