Questions # 91:

For an upcoming project kickoff. a PM is looking for a way to illustrate roles for major project activities. Which of the following would be the MOST useful option?

Options:

A.

Resource plan

B.

Organizational chart

C.

Project charter

D.

RACI chart

Questions # 92:

During the planning phase, a PM reviews the SOW from the contractor, grades the full-time equivalents ' resumes, evaluates the titles and salaries, and estimates the number of hours for each milestone by full-time equivalents. The PM is most likely:

Options:

A.

negotiating resources.

B.

assigning resources.

C.

assessing the resource pool.

D.

adding resources to the schedule.

Questions # 93:

While managing a project, a PM is assigned to work on a second project. The second project becomes more complex and monopolizes the PM ' s time. The PM learns that a similarly time-consuming project was executed previously in the organization. Which of the following actions should the PM take?

Options:

A.

Perform a root cause analysis.

B.

Organize a stakeholder meeting

C.

Escalate the issue to the CCB

D.

Contact the PMO for assistance.

Questions # 94:

A system was implemented, and testing was successfully completed. Which of the following should the project manager do NEXT?

Options:

A.

Validate against the scope statement and ask for sign-off.

B.

Run a control chart to ensure the quality of the deliverables.

C.

Review the risk register and close up residual risks.

D.

Start the training and handoff for the operations team.

Questions # 95:

Which of the following activities would force a team to remove a new package and leave the previous one during a smoke test?

Options:

A.

Rollback plan

B.

Downtime stage

C.

Maintenance window

D.

Validation checks

Questions # 96:

During project initiation, a project manager needs to establish the communication channel that will be used to deliver weekly presentations to stakeholders who are across the country. Which of the following would be the best communication channel to use?

Options:

A.

In-person meetings

B.

Email

C.

Telephone

D.

Videoconference

Questions # 97:

A software development team completed the development and testing of a new accounting software system for a client. Which of the following should the team do next?

Options:

A.

User acceptance testing

B.

Unit testing

C.

Performance testing

D.

Audits and inspections

Questions # 98:

Stakeholders ask the PM to provide an updated budget. Which of the following is the most important reason to update a project ' s budget during the execution phase?

Options:

A.

Evaluate the project ' s communication plan.

B.

Track and manage the project’s financial condition.

C.

Report the project’s risks and issues.

D.

Distribute resources to the project.

Questions # 99:

A project manager and team are reviewing a task that is supposed to take nine days to complete and cost $3,000. There is a 20% chance that an associated risk related to changing requirements could occur, resulting in rework that would add an additional five days and $1,000 in costs. Which of the following represents the total amount that should be budgeted for the task?

Options:

A.

9 days and $3,000

B.

10 days and $3,200

C.

12 days and $3,800

D.

14 days and $4,000

Questions # 100:

A company needs to have structured cabling installed in one of its buildings. Which of the following would be the best document for the company to use to obtain and compare information on cabling services and costs from various vendors?

Options:

A.

RFB

B.

RFQ

C.

RF

D.

RFP