Questions # 121:

During project initiation, a project manager needs to identify goals and deliverables that should be completed by the end of the project and also meet certain cost and time factors. Which of the following would best align with these needs?

Options:

A.

Work breakdown structure

B.

Change log

C.

Project success criteria

D.

Milestone chart

Questions # 122:

A company that is implementing an updated version of its main product hired a new project manager to lead the project. Prior to the start of the project, the sponsor asked the project manager to prepare a report on the defects found in the previous project to avoid a decrease in production. The report shows that the two main defects are related to cosmetic and physical damage to the product. Which of the following charts would BEST prioritize which defects to address?

Options:

A.

Pareto

B.

Run

C.

Control

D.

Histogram

Questions # 123:

Which of the following communication tools would a project manager use to broadcast information without being assured the information will be received?

Options:

A.

Telephone

B.

Videoconference

C.

Face-to-face

D.

Email

Questions # 124:

A company is working on a software development project that involves an external customer. Which of the following describes a project manager ' s responsibility within this type of project?

Options:

A.

Manage the project schedule.

B.

Define the functional requirements.

C.

Develop components for the software.

D.

Assess and authorize security policies.

Questions # 125:

Which of the following criteria would favor using the agile methodology to manage an upcoming project?

Options:

A.

Strong projectized organization

B.

Medium risk

C.

Lack of resources

D.

Multiple undefined tasks

Questions # 126:

During the execution of a project, a project manager wanted to discover how the number of worked hours was affecting the quality of given tasks. For a two-month period, the following data was documented:

Average worked hours

Which of the following describes the result?

Options:

A.

A negative correlation exists between the number of mistakes and the working hours.

B.

No correlation exists between the number of mistakes and the working hours.

C.

A low correlation exists between the working hours and the number of mistakes.

D.

A positive correlation exists between the number of mistakes and the working hours.

Questions # 127:

During a project kickoff meeting, the project manager wants to set expectations for all of the team members. Which of the following actions should the project manager take to accomplish this goal?

Options:

A.

Assign tasks and responsibilities to the team members

B.

Provide an overview of the project objectives and timeline

C.

Develop a project communication plan

D.

Set a meeting cadence for the rest of the project

Questions # 128:

A new project has been assigned to a project manager. In order to move forward with the project charter, which of the following should the project manager work with to define the success criteria for the initiative?

Options:

A.

Lead architect

B.

Project sponsor

C.

Program manager

D.

Scrum master

Questions # 129:

Which of the following is an intended outcome of a stand-up meeting?

Options:

A.

To identify team members for next tasks

B.

To identify future tasks

C.

To identify stakeholders for next tasks

D.

To identify blocking tasks

Questions # 130:

Which of the following best describes the reason a chat messaging service would be used as the primary form of communication for a project team?

Options:

A.

The team is working in different rooms within the same building.

B.

The team is working remotely two days per week.

C.

The team has members distributed around the world in different time zones.

D.

The team is based in the same office but has a large number of members.