Questions # 131:

Given the following information:

Which of the following represents the critical path of the project?

Options:

A.

A-C-F-I-J

B.

A-C-F-H-J

C.

A-B-D-G-J

D.

A-B-E-G-J

Questions # 132:

A project ' s QA team needs to validate functionality in a timely and cost-effective way to ensure good coverage every time a new change is integrated. Which of the following test should the team execute?

Options:

A.

Sanity

B.

Manual

C.

Automated

D.

Regression

Questions # 133:

A project manager is managing a virtual team across the country. As reported in the retrospective, the team morale has decreased due to additional production issues. Which of the following meeting tools is the best option to record results in the retrospective?

Options:

A.

Presentation

B.

Wiki

C.

Chat

D.

Polling

Questions # 134:

A utility company issued a directive stating that projects impacting operating systems will not be executed during hurricane season. Which of the following is being acknowledged by this directive?

Options:

A.

Company brand value

B.

National environments

C.

Standard operating procedures

D.

Local emergency policies

Questions # 135:

As a result of lessons learned, a project manager convenes a meeting to understand the poor quality of the project documentation. During the meeting, project team members provide insights from their perspectives and discussions with group members. Which of the following is the project team doing?

Options:

A.

Executing the approved contingency plan

B.

Constructing an Ishikawa diagram to determine the root cause

C.

Using a Pareto chart to prioritize the different causes

D.

Engaging the senior management team in regard to the issue

Questions # 136:

A team found a deficiency in an application and is proposing improvements, but the sponsor requests a business case. Which of the following best describes the intended objective of the business case?

Options:

A.

To identify the potential risk and issues for the project

B.

To determine the timeline and budget of the project

C.

To define the specific tasks required to create the project

D.

To specify what problem is being solved by the project

Questions # 137:

A client provides a project plan to the assigned project manager and suggests that the project manager and team just need to execute the plan. Upon further investigation, the document contains:

• Purpose

• Scope of work

• Location of work

• Period of performance

• Deliverables schedule

• Applicable standards

• Acceptance criteria

• Special requirements

• Payment schedule

Which of the following documents did the client provide to the project manager?

Options:

A.

RFP

B.

WBS

C.

SLA

D.

SOW

Questions # 138:

A fix that was not submitted to the CCB for approval was applied to an application. Although the change did not have negative consequences, the sponsors expressed concern to the project manager. Which of the following should the project manager do first to prevent this situation from reoccurring?

Options:

A.

Meet with the team and highlight the importance of change management.

B.

Roll back the process and submit a change request.

C.

Document the event as a lesson learned.

D.

Remove the team member who bypassed the CCB process.

Questions # 139:

A project team gathers weekly to review its progress. Which of the following is the project manager MOST likely to have prepared to ensure team members who are absent remain informed about assignments?

Options:

A.

Status report

B.

Project plan

C.

Change log

D.

Meeting minutes

Questions # 140:

A project manager needs to ensure that the products produced during the project meet the highest quality standards and that team members understand the importance of these standards. Which of the following should the project manager do?

Options:

A.

Train the team members.

B.

Assess the resource pool.

C.

Develop a QA plan.

D.

Create RACI matrix.