Questions # 136:

Which of the following can be used as an input for Define Scope?

Options:

A.

Product analysis

B.

Project charter

C.

Scope baseline

D.

Project scope statement

Questions # 137:

The group technique that enhances brainstorming with a voting process used to rank the most useful ideas for prioritization is called the:

Options:

A.

majority rule technique.

B.

nominal group technique.

C.

Delphi technique,

D.

idea/mind mapping technique.

Questions # 138:

When a permitting agency takes longer than planned to issue a permit, this can be described as a risk:

Options:

A.

event.

B.

response,

C.

perception.

D.

impact.

Questions # 139:

Which of the following is a tool or technique used in the Determine Budget process?

Options:

A.

Variance analysis

B.

Three-point estimating

C.

Bottom-up estimating

D.

Historical relationships

Questions # 140:

Which technique is utilized in the Control Schedule process?

Options:

A.

Performance measure

B.

Baseline schedule

C.

Schedule network analysis

D.

Variance analysis

Questions # 141:

The total of the planned value (PV) is also known as:

Options:

A.

work breakdown structure (WBS).

B.

schedule target.

C.

performance measurement baseline (PMB).

D.

earned value baseline.

Questions # 142:

Which type of dependency is contractually required or inherent in the nature of the work?

Options:

A.

External

B.

Lead

C.

Discretionary

D.

Mandatory

Questions # 143:

Expected monetary value (EMV) is computed by which equation?

Options:

A.

Value of each possible outcome multiplied by probability of occurrence

B.

Value of each possible outcome multiplied by probability of non-occurrence

C.

Multiplying the value of each possible outcome by the probability of occurrence and adding the products together

D.

Multiplying the value of each possible outcome by the probability of non-occurrence and adding the products together

Questions # 144:

The technique of subdividing project deliverables into smaller, more manageable components until the work and deliverables are defined to the work package level is called:

Options:

A.

a control chart.

B.

baseline.

C.

Create WBS.

D.

decomposition.

Questions # 145:

Which baselines make up the performance measurement baseline?

Options:

A.

Scope baseline, cost baseline, and schedule baseline

B.

Scope baseline, project management baseline, and quality baseline

C.

Cost baseline, schedule baseline, and risk baseline

D.

Cost baseline, project management baseline, and schedule baseline

Questions # 146:

Identify Stakeholders is the process of identifying all of the people or organizations impacted by the project and documenting relevant information regarding their interests in, involvement in, and impact on the project:

Options:

A.

manager.

B.

success.

C.

deadline.

D.

scope.

Questions # 147:

Who determines which dependencies are mandatory during the Sequence Activities process?

Options:

A.

Project manager

B.

External stakeholders

C.

Internal stakeholders

D.

Project team

Questions # 148:

Which of the following is a statistical concept that calculates the average outcome when the future includes scenarios that may or may not happen?

Options:

A.

Sensitivity analysis

B.

Three-point estimate

C.

Modeling and simulation

D.

Expected monetary value analysis

Questions # 149:

At which stage of team development do members begin to work together, adjust work habits, and trust each other?

Options:

A.

Forming

B.

Storming

C.

Norming

D.

Performing

Questions # 150:

Plan-do-check-act is also known as:

Options:

A.

prevention over inspection.

B.

statistical sampling.

C.

management responsibility,

D.

continuous improvement.