Questions # 181:

Which is the correct formula for calculating expected activity cost for three-point estimating?

Options:

A.

Ce = (C0 + 6Cm + Cp)/4

B.

Ce = (6C0 + Cm + Cp)/4

C.

Ce = (C0 + 4Cm + Cp)/6

D.

Ce = (C0 + C„, + 4Cp) / 6

Questions # 182:

Define Activities and Estimate Activity Resources are processes in which project management Knowledge Area?

Options:

A.

Project Time Management

B.

Project Cost Management

C.

Project Scope Management

D.

Project Human Resource Management

Questions # 183:

Another name for an Ishikawa diagram is:

Options:

A.

cause and effect diagram.

B.

control chart.

C.

flowchart.

D.

histogram.

Questions # 184:

Which piece of information is part of the WBS Dictionary?

Options:

A.

Responsible organization

B.

Change requests

C.

Validated deliverables

D.

Organizational process assets

Questions # 185:

Changes to formally controlled documentation, plans, etc. to reflect modified or additional ideas or content are known as:

Options:

A.

updates.

B.

defect repairs.

C.

preventive actions.

D.

corrective actions.

Questions # 186:

Which technique helps to determine the risks that have the most potential impact on a project?

Options:

A.

Cost risk simulation analysis

B.

Expected monetary value analysis

C.

Modeling and simulation

D.

Sensitivity analysis

Questions # 187:

The key benefit of the Monitoring and Controlling Process Group is the ability to:

Options:

A.

establish and manage project communication channels, both external and internal to the project team.

B.

influence the stakeholders that want to circumvent integrated change control so that their changes are implemented.

C.

monitor the ongoing project team against the team performance assessments and the project performance baseline.

D.

observe and measure project performance regularly and consistently to identify variances from the project management plan.

Questions # 188:

The project manager needs to review the templates in use. The templates are part of the:

Options:

A.

Enterprise environmental factors.

B.

Historical information,

C.

Organizational process assets.

D.

Corporate knowledge base.

Questions # 189:

A required input for Create WBS is a project:

Options:

A.

quality plan.

B.

schedule network.

C.

management document update.

D.

scope statement.

Questions # 190:

Which of the following correctly explains the term "progressive elaboration'?

Options:

A.

Changing project specifications continuously

B.

Elaborate tracking of the project progress

C.

Elaborate tracking of the project specifications with a change control system

D.

Project specifications becoming more explicit and detailed as the project progresses

Questions # 191:

Which of the following is a conflict resolution technique that emphasizes areas of agreement rather than areas of difference?

Options:

A.

Compromising

B.

Collaborating

C.

Smoothing

D.

Problem Solving

Questions # 192:

Control charts, flowcharting, histograms, Pareto charts, and scatter diagrams are tools and techniques of which process?

Options:

A.

Perform Quality Control

B.

Perform Quality Assurance

C.

Plan Quality

D.

Report Performance

Questions # 193:

What is the responsibility of the project manager and the functional manager respectively?

Options:

A.

Oversight for an administrative area; a facet of the core business

B.

Achieving the project objectives; providing management oversight for an administrative area

C.

A facet of the core business; achieving the project objectives

D.

Both are responsible for achieving the project objectives.

Questions # 194:

Which process involves identifying and documenting the logical relationships between project activities?

Options:

A.

Develop Schedule

B.

Sequence Activities

C.

Create WBS

D.

Applying leads and lags

Questions # 195:

Which tool or technique is used in Manage Stakeholder Expectations?

Options:

A.

Stakeholder management strategy

B.

Communication methods

C.

Issue log

D.

Change requests