Questions # 16:

What is the definition of Direct and Manage Project Execution?

Options:

A.

Integrating all planned activities

B.

Performing the activities included in the plan

C.

Developing and maintaining the plan

D.

Execution of deliverables

Questions # 17:

What is the function of a Project Management Office (PMO)?

Options:

A.

To focus on the coordinated planning, prioritization, and execution of projects and subprojects that are tied to the parent organizations or the client's overall business objectives.

B.

To coordinate and manage the procurement of projects relevant to the parent organization's business objectives and to administer the project charters accordingly.

C.

To administer performance reviews for the project manager and the project team members and to handle any personnel and payroll issues.

D.

To focus on the specified project objectives and to manage the scope, schedule, cost, and quality of the work packages.

Questions # 18:

What is the difference between the critical path and the critical chain?

Options:

A.

Scope changes

B.

Resource limitations

C.

Risk analysis

D.

Quality audits

Questions # 19:

Which tool and technique identifies inefficient and ineffective policies, processes, and procedures?

Options:

A.

Scope audits

B.

Scope reviews

C.

Quality audits

D.

Control chart

Questions # 20:

Which of the following involves making information available to project stakeholders in a timely manner?

Options:

A.

Plan Communications

B.

Performance reporting

C.

Project status reports

D.

Distribute Information

Questions # 21:

The formal and informal interaction with others in an organization industry, or professional environment is known as:

Options:

A.

negotiation

B.

organizational theory

C.

meeting

D.

networking

Questions # 22:

Which Develop Schedule tool and technique produces a theoretical early start date and late start date?

Options:

A.

Critical path method

B.

Variance analysis

C.

Schedule compression

D.

Schedule comparison bar charts

Questions # 23:

Which of the following is a narrative description of products, services, or results to be delivered by a project?

Options:

A.

Project statement of work

B.

Business case

C.

Accepted deliverable

D.

Work performance information

Questions # 24:

What is an objective of the Develop Project Team process?

Options:

A.

Feelings of trust and improved cohesiveness

B.

Ground rules for interaction

C.

Enhanced resource availability

D.

Functional managers becoming more involved

Questions # 25:

Sharing good practices introduced or implemented in similar projects in the organization and/or industry is an example of:

Options:

A.

quality audits

B.

process analysis

C.

statistical sampling

D.

benchmarking

Questions # 26:

The process of identifying and documenting the specific actions to be performed to produce the project deliverables is known as:

Options:

A.

Define Activities.

B.

Sequence Activities.

C.

Define Scope.

D.

Control Schedule.

Questions # 27:

Which type of analysis is used to examine project results through time to determine if performance is improving or deteriorating?

Options:

A.

Control chart

B.

Earned value

C.

Variance

D.

Trend

Questions # 28:

What is the term assigned to products or services having the same functional use but different technical characteristics?

Options:

A.

Scope

B.

Quality

C.

Specification

D.

Grade

Questions # 29:

Which technique is used in Perform Quantitative Risk Analysis?

Options:

A.

Sensitivity analysis

B.

Probability and impact matrix

C.

Risk data quality assessment

D.

Risk categorization

Questions # 30:

What is the name of the statistical method that helps identify which factors may influence specific variables of a product or process under development or in production?

Options:

A.

Failure modes and effects analysis

B.

Design of experiments

C.

Quality checklist

D.

Risk analysis