Questions # 121:

A member of a project's development team approaches the team lead and requests database administrator training. The team member believes that their inability to handle this work, and to rely on outside specialists, is impacting team velocity.

What should the agile team lead do?

Options:

A.

Send the member to training

B.

Ask the outside specialists if database administration is required from the team

C.

Send one member to training only after asking the team if there is an issue with the current workflow

D.

Wait until all members of the team can attend training

Questions # 122:

Halfway through the execution of an agile project, a retrospective meeting is held. One of the team members believes that the actual time and cost to complete the work has consistently been greater than what was originally estimated.

Which of the following activities should be performed next?

Options:

A.

The product owner should reduce the scope of the project so that the items delivering the highest business value can be completed.

B.

The team should perform a spike to conduct research on their technical solutions and prove their viability.

C.

The team should consolidate small stories into larger ones so that there are less work items to be estimated.

D.

The team should reevaluate time and cost estimates to reflect the latest understanding of the work effort.

Questions # 123:

A backlog for a project has been prioritized and a sprint has begun. A security issue has been revealed that needs to be addressed or large security vulnerabilities will be exposed.

How should the project manager proceed?

Options:

A.

Consult with the product owner to prioritize the new work at a higher level.

B.

Consult with the project sponsor and project team to resolve the issue.

C.

Consult with the project team to rework the existing estimates.

D.

Consult with the product owner and project team.

Questions # 124:

A team's technical lead believes that manual testing tasks should be conducted by junior team members below their level. The junior team members think it is unfair and refuse the tasks.

What should the Scrum Master do?

Options:

A.

Tell the technical lead to do the testing

B.

Facilitate an open and focused team discussion that reinforces team agreements

C.

Ask the team manager to advise the technical lead that all tasks are important

D.

Encourage the team to take ownership of the delivery

Questions # 125:

What should the agile project leader do?

Options:

A.

Bring up the new member's impediments at the next meeting to demonstrate team support of input

B.

Assure the new member that inputs on impediments are valued and demonstrate this at the next meeting

C.

Have a senior lead work with the new member to avoid a negative impact on team productivity

D.

Privately work with the new member to address any impediments

Questions # 126:

A scrum master is working with a team on a complex software project that is scheduled to run for 2 years with a series of product releases. The scrum master is responsible for planning the project for the next 6 months and has advised planning the project up front.

What should the scrum master do?

Options:

A.

Add the releases into a roadmap with milestones and activities.

B.

Identity dedicated tasks and activities with regular feedback loops.

C.

Deliver in small and continuous iterative releases.

D.

Identify the requirements' schedule within set time scales.

Questions # 127:

Early in a project, stakeholder analysis is performed; however, an organizational restructure redefines key roles. What should the project team do?

Options:

A.

Note the changes to the restructure and roles that affect team activities

B.

Use direct engagement and two-way conversation to update the stakeholder analysis for any new stakeholder requirements.

C.

Email a copy of the project vision to those redefined for key roles and ask if they need to be involved in the project

D.

Obtain a copy of the redefined key roles to update the stakeholder analysis

Questions # 128:

A key stakeholder feels they do not understand the project at a comprehensive level.

What should the Agile practitioner do?

Options:

A.

Send daily status emails to let stakeholders know what progress is being made.

B.

Invite stakeholders to attend daily Scrum meetings to get feedback.

C.

Share information via interactive methods such as a brainstorming session.

D.

Build the feature backlog and then solicit stakeholder feedback.

Questions # 129:

During a coaching session, an agile project manager discussed embracing communication to keep all stakeholders aligned. The agile project manager recently had a discussion with their team and decided to display a product roadmap.

What is the agile project manager trying to show?

Options:

A.

The project's total number of story points.

B.

Product releases and what will be included.

C.

The number of completed user stories.

D.

Where the team is in the project life cycle.

Questions # 130:

A product owner worked with the customer to define the success criteria for the launch of a new product in the manufacturing industry. The project team responsible for development is seeking guidance on what to develop first.

Which two actions should the product owner take? (Choose two.)

Options:

A.

Work with the team to establish goals for the product at the beginning of each scheduled iteration.

B.

Send the team the latest version of the release plan so they can provide feedback.

C.

Invite the customer to the sprint planning meeting to explain what is deemed most critical to their business.

D.

Ensure all iteration goals are fully developed at the beginning of the project.

E.

Refine the product backlog and identify the Minimum Viable Product