Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code = getmirror
Pass the PMI Agile PMI-ACP Questions and answers with ExamsMirror
Exam PMI-ACP Premium Access
View all detail and faqs for the PMI-ACP exam
705 Students Passed
93% Average Score
97% Same Questions

A project team's manager is responsible for delivering a specific initiative for the organization. They are preparing for a monthly meeting where the manager will present on the current state of this initiative. The agile project lead sends the manager the following email with the current initiative status (see Exhibit A).
How many sprints will be needed to complete the entire backlog?
An agile project manager is leading an international project involving a global team consisting of members from very different cultures, countries, and time zones. The agile project manager is aware that similar projects with distributed teams have led to serious conflicts.
What should the agile project manager do to promote trust and collaboration?
Over the last two sprints, a number of potential problems have threatened the team's ability to hit the targeted release date.
What should the agile practitioner do?
Who should the Scrum Master invite to the meeting?
A team worked with a customer to estimate all user stories for the must have features. During release planning sessions, the customer indicated they prefer 3-week iterations that begin on Thursdays and end on Wednesdays. The team spent several days determining which stories should be developed for iteration 0 and understanding the customer’s priorities for the remaining stories. The project sponsor attends the Friday meeting and requests a high-level estimate of when they can invite the chief executive officer (CEO) to a demonstration of the minimum viable product (MVP).
What should the team tell the sponsor at this point in the planning process?
After performing three sprints, the product owner and sponsor request an accurate schedule indicating when all releases will be delivered.
What should the agile practitioner do?
Just before a scheduled product launch, the customer declined to accept the final deliverable after seeing the demo. What should the project manager do to prevent this in the future?
On an agile project, it is important to identify and engage business stakeholders throughout the project and to ensure the team understands the stakeholders' business needs. Which option supports this idea?
Following approval of a business case, a company will introduce a new mobile app for customers to place orders. Time to market is a key concern. The product has entered into the 3rd iteration, but the team is concerned because they feel the technical designs do not meet the agreed-on definition of done (DoD). An agile coach has been hired to help validate product delivery against business requirements.
What should the agile coach do?

A product owner is working on a special agile project for the automobile industry. The project team is responsible for all of the issues related to vehicle electronic control units. The team has observed a significant backlog of items in the “In progress' column (Refer to the kanban board). This accumulation is causing delays in task completion and impacting overall project timelines. The team operates in a dynamic environment where requirements frequently change, and stakeholders demand quick turnarounds.
What should the project team adopt to address this issue and improve task flow, considering all the demands?
TOP CODES
Top selling exam codes in the certification world, popular, in demand and updated to help you pass on the first try.

Normal sprint velocity: 5 story points per sprint
Reduced velocity for sprints 4-6: 4 story points per sprint
First 3 sprints: 5 points per sprint → 5 × 3 = 15 story points completed
Sprints 4-6: 4 points per sprint → 4 × 3 = 12 story points completed
Remaining story points after sprint 6: 72 - (15 + 12) = 45 story points
Remaining sprints needed at normal velocity (5 story points per sprint): 45 ÷ 5 = 9 sprints
Sprints 1-6: Already planned.
Additional 9 sprints needed.