Questions # 1:

A new project is in the planning phase. The business owner believes that, since the timeline is aggressive, requirements elicitation should begin as soon as possible.

Which activity should the business analyst initiate before beginning requirements elicitation?

Options:

A.

Prepare the requirements traceability matrix.

B.

Define how the solution will be evaluated.

C.

Draft a high-level data model.

D.

Document how the relevant systems interact.

Questions # 2:

A business analyst and stakeholders have completed documentation of the acceptance criteria for the requirements of a new vehicle leasing database. A concern is raised that some of the key performance indicators may not validate the desired benefits of the implementation.

What should the business analyst do to ensure that the business need can be validated?

Options:

A.

Document an assumption.

B.

Document a constraint.

C.

Document a defect.

D.

Document a business rule.

Questions # 3:

The requirements traceability matrix should primarily be used to:

Options:

A.

identify the risks associated with dependent requirements.

B.

define a convention to map the requirements to their sources.

C.

ensure that all requirements have been met.

D.

address the responsibility owner for each requirement.

Questions # 4:

Testing on a project has been completed. In order to proceed with deployment, a decision is needed.

Who should the business analyst contact to review the testing results and get approval to proceed with deployment?

Options:

A.

The tester identified in the testing strategy

B.

The person identified in the RACI matrix

C.

The project manager identified in the project charter

D.

The project sponsor identified in the scope document

Questions # 5:

The project manager is beginning to prepare for a test readiness review with the customer. The project manager knows that the customer will want a summary of requirements that have been rejected or deferred. The project manager has requested that the business analyst provide a list of rejected and deferred requirements.

What should the business analyst have done to complete this request?

Options:

A.

A Set up a change control board to track the number of rejections.

B.

Limit the number of rejected requirements on the project.

C.

Track rejected requirements in the system requirements verification matrix.

D.

Spend more time up-front reviewing the requirements to limit rejections.

Questions # 6:

A business analyst is working on a project to update the user interface for a legacy procurement system. An end user raises concerns that the new solution will not support their core business processes.

How could the business analyst address the end user's concerns about the new interface?

Options:

A.

Consult the stakeholder register to evaluate if the user has authority to influence the project.

B.

Develop a prototype to gather functional requirements.

C.

Develop a use case package to support the user interface.

D.

Document the business data objects using an entity relationship diagram.

Questions # 7:

The sales team of a company has won a time-and-material project. The business analyst discovers that the sales team has underestimated the required budget and schedule.

Which course of action should the business analyst take?

Options:

A.

Refrain from working on the project and request that the customer cancel the contract.

B.

Accept the contract, and then notify the customer about the potential for a cost overrun.

C.

Accept the contract, and deliver only the requirements that fit within the budget and schedule.

D.

Develop a requirements baseline document and use it to negotiate the scope in the contract.

Questions # 8:

A business analyst anticipates receiving requirements changes. What should the business analyst do to avoid scope creep?

Options:

A.

Meet with the stakeholder and discuss timeline impact.

B.

Refer changes to the project manager.

C.

Define requirements baseline and implement a change control process.

D.

Implement only the original requirements.

Questions # 9:

The business analyst has completed the requirements gathering and documentation processes in developing a baseline document. Several signoffs are needed. During the joint review process with the key stakeholders, the stakeholders announce that they are still not ready to sign off due to a communication gap.

Which technique should the business analyst have followed to ensure consensus?

Options:

A.

The business analyst should have performed a complete review of each requirement with one of the stakeholders’ peers before the meeting.

B.

The business analyst should have performed a complete review of each requirement with the key stakeholders prior to the meeting.

C.

The business analyst should have reviewed the requirements of the project sponsor first before reviewing other requirements.

D.

The business analyst should have invited the key stakeholders to the meeting.

Questions # 10:

A type of requirements document that would be the most valuable to a database administrator would be:

Options:

A.

a data flow diagram.

B.

a business process diagram.

C.

an entity relationship diagram.

D.

an object diagram.