Questions # 41:

A company wants to procure a tool to improve customer satisfaction and loyalty. Which of the following documents would provide basis for analyzing vendor products?

Options:

A.

Storyboard

B.

Project charter

C.

Business case

D.

Survey

Questions # 42:

A company is developing a new e-commerce platform to enter a new market segment. Development is well under way when the government issues a new set of regulations.

Which course of action should the business analyst take?

Options:

A.

Evaluate if the new set of regulations is aligned with the business case.

B.

Evaluate the impact of the change on the project schedule.

C.

Obtain management sign-off on the new set of regulations.

D.

Check the traceability matrix to identify affected use cases.

Questions # 43:

A project team has been assembled to streamline accounts payable processes in all divisions of the company. As part of the planning activities, the business analyst is working to identify stakeholders.

Which of the following techniques would the business analyst use to identify stakeholders?

Options:

A.

Brainstorming

B.

State diagram

C.

Estimation

D.

Prototyping

Questions # 44:

A business analyst has been assigned to a project that will design and build two new bridges and, at the same time, redesign a failing bridge for a local structural engineering company. All three bridges must be constructed and meet all safety requirements before flood season next spring.

How would the business analyst define the scope of this project?

Options:

A.

Perform a work breakdown structure.

B.

Perform a feasibility study.

C.

Perform process modelling.

D.

Perform a structured walkthrough.

Questions # 45:

During the project execution phase, the client requests the addition of a new feature. Which of the following would allow the business analyst to determine the impact for the specific requirement change?

Options:

A.

Requirements cards

B.

Requirements baseline

C.

Requirements management tool

D.

Requirements traceability matrix

Questions # 46:

When managing a product backlog, which statement best describes how to determine the value of backlog items?

Options:

A.

The stakeholders provide recommendations with the product owner having the final say.

B.

The stakeholders follow the value-ranking criteria.

C.

The stakeholders do not typically play a major role.

D.

The stakeholders provide input about backlog value when the item is first identified.

Questions # 47:

A business analyst has been assigned to Project Y. After a requirements gathering session, the project manager asks the business analyst to identify which requirements would be considered in scope and out of scope, based on the business need.

What document should the business analyst use to determine the relationship of the requirement to the business need?

Options:

A.

Traceability matrix

B.

Requirements management plan

C.

Requirements package

D.

Reliability matrix

Questions # 48:

A business analyst has started a project for a system enhancement. In order to determine how the requirements will be approved, the business analyst schedules a meeting with the stakeholders to discuss the proposed approval process.

Which measure of effective decision making allows the business analyst to finalize the process for requirement approval?

Options:

A.

The requirements verification process is documented.

B.

The requirements elicitation process is documented.

C.

The requirements validation process is documented.

D.

The requirements approval process is documented.

Questions # 49:

While preparing a business case, an experienced business analyst faces difficulty in deciding which of three different solution options to recommend. The senior vice president (SVP) who requested the business case favors an outsourced solution; however, an analysis

favors a custom-developed solution, either built internally or using contract labor.

To prepare the recommendation, what should the business analyst do?

Options:

A.

Perform solution evaluation.

B.

Formulate a weighted-ranking matrix.

C.

Review the stakeholder analysis.

D.

Recommend the SVP's choice, as it is most likely to be adopted.

Questions # 50:

Which technique allows the collection of the maximum number of ideas on a subject from a group without considering the validity or practicality of the ideas?

Options:

A.

Brainstorming

B.

Interviewing

C.

Prototyping

D.

Surveying