Questions # 51:

A business analyst has been assigned to a project team that is redesigning the company's website. The business analyst has been documenting the relationships between requirements and has found requirements that do not trace to a business need.

Which type of requirements are these?

Options:

A.

In-scope

B.

Tested

C.

Implemented

D.

Out-of-scope

Questions # 52:

An organization is evaluating the possibility of conducting business internationally. Which factors should be investigated at the onset of the initiative?

Options:

A.

Deliverables to be produced

B.

Impacts on requirements baseline

C.

External dependencies

D.

Change control processes

Questions # 53:

A project affects the marketing unit and procurement unit. The project manager gives the business analyst an overview of the project for the first time.

What should the business analyst do immediately after the discussion?

Options:

A.

Schedule time with the process owners.

B.

Put the information into a project plan.

C.

Develop an issues log.

D.

Assess the risks for the project.

Questions # 54:

Which of the following tools will help facilitate the decision-making process when stakeholders do not agree on the value of an initiative?

Options:

A.

PEST analysis

B.

B. Force-field analysis

C.

Feasibility analysis

D.

Gap analysis

Questions # 55:

A company is awarded a contract to design and build a custom product. The contract references a detailed technical specification. What is the best action to take to ensure the design meets customer requirements?

Options:

A.

Create a system requirements verification matrix to trace the design to the technical requirements and include verification methods.

B.

Conduct a one-on-one interview with each member of the technical team to ensure that they understand the customer's specification.

C.

Generate a design package for the product and ask the customer to verify that the design meets his or her technical needs.

D.

Develop a test plan to verify that the product meets the performance requirements in the technical specification.

Questions # 56:

A business analyst in organization Y is assigned to elicit requirements in a project within a defined timeline. The business analyst has identified and invited key stakeholders to a requirements workshop. However, the stakeholders are not giving clear and concise requirements; their opinions about requirements are changing and conflicting with each other in the meeting. In the end, the business analyst could not elicit and define the requirements and therefore adjourned the meeting.

Which tool or technique could have been used by business analyst to avoid this situation?

Options:

A.

Prototyping

B.

Surveys

C.

Document analysis

D.

Decision tree

Questions # 57:

Through user acceptance testing, a software flaw was identified. What should the business analyst do next as part of the root cause analysis in order to analyze and resolve the discrepancy?

Options:

A.

Create a fishbone diagram.

B.

Create an interface analysis.

C.

Create a Delphi estimation.

D.

Create a functional decomposition.

Questions # 58:

In the middle of a project, a new requirement was added to the scope. The business analyst must determine if any impacts, dependencies, or risks are associated with the addition to the scope.

What task should the business analyst perform in order to identify these impacts?

Options:

A.

Manage solution scope.

B.

Manage requirements traceability.

C.

Manage requirements prioritization.

D.

Manage assumptions and constraints.

Questions # 59:

A stakeholder wants to modify an existing feature. Which of the following would be used to determine the scope of the change on the product?

Options:

A.

Project schedule and cost baseline

B.

Requirements traceability matrix

C.

Requirements attributes table

D.

Sequence diagram

Questions # 60:

A company has completed a major project within time, cost, and scope and satisfied high-level quality standards and marketing requests. However, the product was considered a complete failure by shareholders and the market due to low return on investment.

From the business analysis perspective, the main reason for this business failure was a failure to:

Options:

A.

set the product positioning.

B.

review and evaluate market expectations.

C.

gather the appropriate usability requirements.

D.

establish measurable success criteria in the business case.