Questions # 1:

Gary is the project manager of the NHF project, which is a part of a program in his organization. According to the PMBOK, how will Gary provide feedback to programs and portfolios?

Options:

A.

Status meetings

B.

Push communications

C.

Regular communications

D.

Status reports and change requests

Questions # 2:

Sam is the project manager of the NQQ project. He and the project team have completed the stakeholder identification process for his project. What is the main output of the identify stakeholders process?

Options:

A.

Communications management plan

B.

Stakeholder register

C.

Requirements

D.

Stakeholder management strategy

Questions # 3:

You are the project manager of the JKM Project for your organization. Your project is supposed to be 60 percent complete but you are only 45 percent complete. The project has an assigned budget of $765,000 but you have already spent $365,000 to reach this point in the project due to some errors and rework. Management is pressing you on when you'll complete the project and how much the project will likely cost based on the current performance. You need to tell management what the project's current cost performance index (CPI) is. What value should you report to management based on your project's performance?

Options:

A.

$306,000

B.

.94

C.

$344,250

D.

.75

Questions # 4:

The figure given below demonstrates the communication model for a project. What role does the component E play in the communications model?

Question # 4

Options:

A.

Static

B.

Deterrent

C.

Noise

D.

Barrier

Questions # 5:

Mary is the project manager for her company. She's working with the project team to compress the project schedule as the project must be completed by December 30. For some of the project activities, she and the project team have agreed to crash the project work. What must be true of these project activities for crashing to be acceptable?

Options:

A.

The activities must be of fixed duration.

B.

The activities must be effort-drive.

C.

The activities must not be susceptible to the Law of Diminishing Returns.

D.

The activities must be risk-free.

Questions # 6:

John works as a Project Manager for Blue Well Inc. He is measuring cost efficiency of his project. The key values are provided in the table below:

Question # 6

What is the cost performance index (CPI) of the project at the current point of time?

Options:

A.

0.96

B.

1.082

C.

0.833

D.

1.0625

Questions # 7:

Beth is the project manager for the NHQ project. This project deals with fiber optic cabling in her organizational campus. Tim is the electrical engineer for her company and is the only internal resource that can complete several of the project activities that deal with the fiber optic cables. Because Tim is a highly-skilled resource, he is already scheduled on several projects within the organization and is not available when Beth needs him to complete some of the project activities. This is an example of which term?

Options:

A.

Resource calendar conflict

B.

Matrix network

C.

Organizational process assets

D.

Activity resource requirements

Questions # 8:

Holly is the project manager for her organization. In her project, she has worked with the project team to define when the project team will be utilized in the project, the duration of the project activities, and the sequence in which the project work must be completed. During several phases of her project, the project team will need to work more than fifty hours per week. The project team members have agreed this is necessary and they're willing to do the work to complete the project. Management, however, has not approved Holly's schedule based on the overtime the scheduling will require. They have set a limit on the project schedule of 45 hours per week. What is this limit technically called? Each correct answer represents a complete solution. Choose all that apply.

Options:

A.

Constraint

B.

Assumption

C.

Execution variance analysis

D.

Resource leveling heuristic

Questions # 9:

You are the project manager of the NHG. The following figure represents your project network diagram.

Question # 9

Management has asked that you add some features to the project scope. Through the change control system these changes are approved and they'll affect Activity I. The duration of Activity I, which is on the critical path, will decrease by three days. What affect does this have on the critical path?

Options:

A.

The critical path will now take 26 days.

B.

The critical path will now take 17 days.

C.

The critical path will now take 23 days.

D.

The critical path will now take 20 days.

Questions # 10:

Which of the following components of the change control system includes the documentation, tracking systems, and defined approval levels necessary for authorizing and controlling changes?

Options:

A.

Scope Verification

B.

Configuration Management System

C.

Project Management Information System

D.

Integrated Change Control