Questions # 81:

Harry works as a project manager for BlueWell Inc. He is determining the budget of the project. According to the PMBOK, there are seven inputs to this process. Which one of the following is NOT an input to the determine budget process?

Options:

A.

Contract

B.

Reserve analysis

C.

Scope baseline

D.

Project schedule

Questions # 82:

You work as a Project Manager for Tech Perfect Inc. Several projects are running under your supervision. Martha, a team leader of a project, informs you about the performance indexes of her project. The schedule performance index (SPI) of her project is 0.835. What does this figure indicate?

Options:

A.

The schedule performance is right on target.

B.

The schedule performance is better than expected.

C.

The cost performance is better than expected.

D.

The schedule performance is below expectation.

Questions # 83:

Complete this sentence:

_________________________ is the process of collecting and distributing performance information including status reports, progress measurements, and forecasts.

Options:

A.

Corrective action

B.

Report performance

C.

Earned value management

D.

Monitor and control project performance

Questions # 84:

You are the project manager of the NHQ project. You are working with your project team to create the project schedule and the project network diagram. In order to start the sequencing of the project activities, you will need a document to identify the result of project phases, key project deliverables, and significant, timeless events in the project. Which of the following documents will you need to help sequence the project work?

Options:

A.

Activity attributes

B.

Activity list

C.

Project scope statement

D.

Milestone list

Questions # 85:

You work as a scheduler for your organization. You are developing a schedule and its constraints for the SAP project. There are nine inputs to develop a project schedule. Which of the following is NOT an input to the schedule development process?

Options:

A.

Work breakdown structure

B.

Activity attributes

C.

Resource calendars

D.

Activity list

Questions # 86:

You work as a project manager for BlueWell Inc. You would like to crash your project to help the project schedule to get back on track. What is the primary danger of crashing?

Options:

A.

Crashing increases project costs.

B.

Crashing is a top-down approach to project completion.

C.

Crashing restricts resource utilization.

D.

Crashing always increases project risks.

Questions # 87:

A project manager is reviewing her project performance. Her project has a BAC of $950,000 and is currently 40 percent complete, though it was scheduled to be 45 percent complete at this time. Her project has spent $387,526. Management would like to know if there is a schedule variance. What is the planned value for this project?

Options:

A.

-$47,500

B.

0.89

C.

$427,500

D.

0.98

Questions # 88:

Holly is a new project manager in your organization. She is working with you on the JHG project and she is confused as to why the project needs a schedule management plan and a schedule baseline. What is the difference between the schedule management plan and the schedule baseline?

Options:

A.

The schedule management plan describes how the schedule will be managed and controlled. The schedule baseline is used to compare with actual results to determine if a change, corrective action, or preventive action is needed.

B.

The schedule management plan describes how the schedule will be managed and controlled. The schedule baseline is used to determine how accurate the schedule management plan has been throughout the project execution.

C.

The schedule baseline describes how the schedule will be managed and controlled. The schedule management plan is used to compare with actual results to determine if a change, corrective action, or preventive action is needed.

D.

The schedule management plan describes how the schedule will be created. The schedule baseline is used to compare with actual results with what the project manager intended.

Questions # 89:

Wendy is the project manager for the NHQ project. She is working with her project to begin creating the project duration estimate. Her organization is in weak matrix and several of the project team members are scheduled to complete work on other projects. What input will most likely be of the biggest assistance as Wendy and the project team begin creating the duration estimate for this project?

Options:

A.

Project charter

B.

Project scope statement

C.

Project communications management plan

D.

Resource calendar

Questions # 90:

You are the project manager for your organization. You are working with your virtual team to create activity duration estimates for your current project. This virtual team is comprised of team members from around the world. Much of this process will be completed by geographical locations though some conferences will require all the team members to participate and to coordinate the activities that will interact between the different sites. The project manager must consider all of the following when creating the activity duration estimates except for which one?

Options:

A.

Project calendar

B.

Critical path

C.

Resource calendar

D.

Time zone differences