Questions # 91:

You work as a project manager for BlueWell Inc. You are in the process of identifying all the people and organization impacted by the project. Mark, a project team member, has some doubts about the inputs of the Identify Stakeholder process. What is referred to as an input to the identify stakeholder process in project communication management?

Options:

A.

Expert judgment

B.

Project charter

C.

Stakeholder analysis

D.

Stakeholder register

Questions # 92:

John works as a project manager for BlueWell Inc. His project has a budget of $795,000 and he has spent $325,000 on the project. But, he has completed only 40 percent of the project work till now. Management wants to know what the project's cost performance index is. What value will John report?

Options:

A.

0.76

B.

0.85

C.

0.80

D.

0.92

Questions # 93:

Della works as a project manager for BlueWell Inc. She has asked her assistant Beth to provide activity duration estimate for an activity. Beth provides Della the following estimate chart:

Question # 93

What will be the activity duration according to the PERT three-point analysis?

Options:

A.

19

B.

24

C.

29

D.

46

Questions # 94:

You are the project manager for your project. Your project is scheduled to last for one year and you are currently forty percent complete with the project. Based on your current performance measurements you have an SPI of .95 and a cost variance of -$24,000. You need to report this information to the management, but you will also need a solution to present with the variance information. Which one of the following can you present to the management as a part of the control schedule tools and techniques for variances?

Options:

A.

Work performance measurements

B.

Corrective actions

C.

Trim the project scope

D.

Causes of variances

Questions # 95:

Gary is the project manager of the NGH project for his organization. He and the project team have created the initial WBS. Before Gary and the project team begin creating the activity list, Gary wants the project team to help him create a unique numbering system for the deliverables identified in the WBS. What numbering system can Gary and the project team apply to the WBS to identify the components of the WBS?

Options:

A.

Code of accounts

B.

Chart of accounts

C.

Component numbering

D.

Activity linkage sequencing

Questions # 96:

You are the project manager of the QAQ Project. The QAQ Project has a BAC of $2,786,121. You are currently 20 percent complete with this project, though you should be 25 percent complete with the project work. The project has consumed $595,000 of the project budget to date. Management has asked you, based on the current project performance, what the project's estimate to complete will be considering the current project schedule variance. What is the ETC for this project?

Options:

A.

$2,975,000

B.

1.02

C.

$139,306

D.

$2,380,000