Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code = getmirror

Pass the PMI Certification PMI-SP Questions and answers with ExamsMirror

Practice at least 50% of the questions to maximize your chances of passing.
Exam PMI-SP Premium Access

View all detail and faqs for the PMI-SP exam


732 Students Passed

85% Average Score

93% Same Questions
Viewing page 6 out of 10 pages
Viewing questions 51-60 out of questions
Questions # 51:

You are the project manager of the NHQ Project. Management has told you that resource leveling will be enforced on your project, but they still want you to complete the project by July 2. With the current resources you have and the resource leveling imposed, you would not be able to finish by the constraint. What document should you update to address this situation?

Options:

A.

Project activity resource requirements

B.

Project schedule management plan

C.

Project scope

D.

Project charter

Questions # 52:

Fred is the project manager of a hotel restoration project. The hotel has 456 rooms. All rooms need to be primed and painted. Before each room can be painted, the primer must cure for twenty-four hours. Fred has arranged these tasks with a finish to start relationship between the priming and the painting. What else should Fred do to account for the twenty-four hours of cure time?

Options:

A.

Fred should add twenty-four hours of lead time to each of the 456 rooms painting activity to account for the primer's curing time.

B.

Fred should add twenty-four hours of lag time to each of the 456 rooms painting activity to account for the primer's curing time.

C.

Fred should add an intermediary task with a duration of twenty-four hours.

D.

Fred should schedule all 456 hotels rooms to be primed first and then schedule all 456 rooms to be painted to ensure time for the curing.

Questions # 53:

Billy is the project manager of the PQW Project and she has an assigned project budget of $655,000. Currently she is 80 percent complete with the project though she was scheduled to be 90 percent done by this date. She has spent $490,000 to date. What should Billy report as her cost performance index (CPI)for this project?

Options:

A.

.07

B.

1.07

C.

$34,000

D.

.89

Questions # 54:

Mary is the project manager for her organization. She is working with the project team to define the project activities. She is concerned about some of the dependencies of the project work, which may affect the project schedule. Which one of the following is the best example of a project constraint that will likely affect the project's ability to finish by a given deadline?

Options:

A.

The project must use internal team members to complete the project work.

B.

The project must adhere to several regulations.

C.

The project must use the BGH company to deliver the software portion of the project.

D.

The project must not exceed $1,250,000.

Questions # 55:

You are the project manager for your organization. You are coaching Allen, a junior project manager, on how the details of the project's critical path are calculated. Examine the figure given below:

Question # 55

What is the critical path of this project?

Options:

A.

ABEHJ

B.

ACFGJ

C.

ADGJ

D.

ACFIJ

Questions # 56:

You are the project manager of the NNN Project. Stakeholders in the two-year project have requested to send status reports to them via email every week. You have agreed and are sending the reports on each Thursday. After six months of the project, the stakeholders are pleased with the project progress and they would like you to reduce the status reports to every two weeks. What process will examine the change to this project process and implement it in the project?

Options:

A.

Project change control process

B.

Perform integrated change control process

C.

Configuration management

D.

Communications management

Questions # 57:

Examine the figure given below.

Question # 57

In this project network diagram, what is the total float for Activity I?

Options:

A.

Three

B.

Zero

C.

Five

D.

One

Questions # 58:

You are the project manager of the GHQ Project. You are working with your project team to create the project network diagram. You have created the PND and are identifying the critical path with your team using your project management information system. All of the activities on the critical path are showing in red in the software that you are using to evaluate the critical path. What are schedule activities on the critical path called?

Options:

A.

Critical activities

B.

Action items

C.

High alert activities

D.

Red rated activities

Questions # 59:

Joe is the project manager of the HJN Project. Joe's project is a renovation of an office building. There must be 30 hours between the painting activity and the carpet activity in the project schedule to eliminate the risk of wet paint getting on the carpet. What is the best approach Joe can do to alleviate this issue?

Options:

A.

Add lead time to the painting activity.

B.

Change the relationship of the carpet activity and the painting activity to finish-to-finish.

C.

Create a dummy activity between the painting activity and the carpet activity for the duration of the drying process.

D.

Add lag time to the carpet activity.

Questions # 60:

Andy is the project manager for his project. Andy and his project team are identifying stakeholders who can significantly impact the project, what the level of participation for each identified stakeholder may be, and classifying the stakeholders by common characteristics, concerns, and their perception of the project. Andy and his project team want to define an approach as a result of this information to gain support from the stakeholders for their project. What should Andy and his project team create in this scenario?

Options:

A.

Stakeholder assessment information

B.

Stakeholder register

C.

Communications management plan

D.

Stakeholder management strategy

Viewing page 6 out of 10 pages
Viewing questions 51-60 out of questions
TOP CODES

TOP CODES

Top selling exam codes in the certification world, popular, in demand and updated to help you pass on the first try.