Questions # 1:

The project manager needs to define key information so that the project board can decide whether to proceed with planning the project in more detail.

In which process should the project manager define this information?

Options:

A.

Starting up a project

B.

Initiating a project

C.

Directing a project

D.

Managing a stage boundary

Questions # 2:

Which describes a management activity within a project?

Options:

A.

Encouraging a project team to continue working on a particularly challenging product

B.

Discussing project objectives with key stakeholders during a requirements gathering workshop

C.

Agreeing a work package with a team manager to deliver products within agreed tolerances

D.

Seeking feedback from team members to ensure they are still aligned to the project's objectives

Questions # 3:

The project manager needs to plan the reviews to confirm whether the expected measurable improvements have been achieved.

Which management product should the project manager produce?

Options:

A.

Benefits management approach

B.

Business case

C.

Quality management approach

D.

End project report

Questions # 4:

What is a description of a leadership activity within a project?

Options:

A.

Understanding and working with different departments outside of the project team

B.

Agreeing a work package with a team manager to deliver products using specific tools

C.

Ensuring that a co-located project team uses the agreed communication methods

D.

Creating a stage plan and product descriptions for the products to be created in the next stage

Questions # 5:

The project manager needs to know what modifications have been proposed to an approved product during the stage. Which management product should the project manager review?

Options:

A.

issue register

B.

issue report

C.

Issue management approach

D.

Risk management approach

Questions # 6:

Which statement about the 'manage by stages’ principle is CORRECT?

Options:

A.

The project board should authorize multiple stages at the same time

B.

The end of a stage should provide a control point for the project board

C.

A project should have fewer, longer stages when the risk exposure is high

D.

A project should have separate stages to plan, deliver and close the project

Questions # 7:

What does qualitative analysis of a risk assess, as a minimum?

Options:

A.

How soon each risk might occur

B.

The fallback plan for each risk

C.

The likelihood and the effect of each risk on objectives

D.

The speed with which the effect of each risk will be felt

Questions # 8:

The project manager needs to document how risk management will be undertaken during the project.

In which step of the 'risk management’ technique should the project manager document this?

Options:

A.

Identify: define context and objectives

B.

Identify: identify threats and opportunities

C.

Assess: prioritize risks

D.

Assess: combine risk profile

Questions # 9:

How does product-based planning help to determine the project approach?

Options:

A.

By Identifying the outputs that the project trust deliver

B.

By planning in detail how to deliver the outputs over a more predictable time scale

C.

By managing constraints to the planned completion date for the project

D.

By dividing the delivery of the project's outputs into stages which do not overlap

Questions # 10:

The team manager has organized a workshop with project stakeholders to define the detailed requirements for a number of outputs.

Which principle is being applied by the team manager as part of the 'people’ element when holding this workshop?

Options:

A.

Focus on products

B.

Tailor to suit the project

C.

Define roles, responsibilities and relationships

D.

Ensure continued business justification