Questions # 31:

Why is change management important in a project?

Options:

A.

It provides clarity on how the culture of an organization needs to adapt over time

B.

It provides processes and management products to use when requesting a change

C.

It provides confidence that the project can meet is objectives and has continued business Justification

D.

It provides a controlled and bidirectional flow of information to key Influencers

Questions # 32:

Which process should be Used to confirm that the project continues to deliver against the strategic objectives?

Options:

A.

Managing a stage boundary

B.

Managing product delivery

C.

Initiating a project

D.

Closing a project

Questions # 33:

What is a description of a purpose of the ‘quality’ practice?

Options:

A.

To enable the project products to meet the documented expectations of the user

B.

To document fundamental information to make rational sneer (Wert commissioning the project

C.

To establish the basis for the project, to enable the work to deliver the project product to be understood

D.

To monitor the allocated work, deal with issues, and allocate additional work if required

Questions # 34:

Which TWO are objectives of the ‘starting up a project’ process?

1. To provide an interface between the corporate layer and the project

2. To provide the required authority to initiate the project

3. To plan the work required for project initiation

4. To provide business justification for initiating the project

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Questions # 35:

Which principle should ensure that a project remains aligned with the objectives of the investing organizations?

Options:

A.

Focus on products

B.

Manage by exception

C.

Tailor to suit the project

D.

Ensure continued business justification

Questions # 36:

According to the 'continued business justification' principle, when is a justifiable reason for a project FIRST needed?

Options:

A.

After the executive has been appointed

B.

When authorized by the corporate, programme management or the customer

C.

Before work to start the project commences

D.

When an organization produces its business plans

Questions # 37:

How often should the 'controlling a stage' process be used during a project?

Options:

A.

Once, for the whole project

B.

For each delivery stage in the project

C.

Whenever the project board meets

D.

Twice, for initiation and for the rest of the project

Questions # 38:

Which statement is CORRECT about the customer and suppliers of a project in a commercial environment?

Options:

A.

Each party may have their own business case for undertaking the project

B.

Both parties must apply the same external governance to the project

C.

The risk appetite should be collaboratively set before the project starts

D.

Management systems need to be unified for successful project delivery

Questions # 39:

Whitt is 3 purpose of the initiating a project’ process?

Options:

A.

To prepare the contract for the project to enable the project board to commit to delivery

B.

To provide the project board with Just Enough Information to decide whether to approve the Initiation stage

C.

To provide the opportunity for the senior user in confirm that they find the project product acceptable

D.

To enable the project board to empower the project manager to work within delegated authority limits

Questions # 40:

Which statement describes the context of the 'initiating a project" process?

Options:

A.

The project is viewed from the perspective of the project board in this process

B.

This process should result in key stakeholders being committed to the project

C.

This process is triggered by the assembly of the project brief

D.

The 'controlling a stage' process will start immediately after this process