Questions # 51:

According to the ‘exception management’ technique, when should the team manager raise an issue?

Options:

A.

When the team manager predicts that a product will cause a stage to exceed its time tolerance

B.

When the team manager identifies that a product is going to be delivered late

C.

when the team manager predicts that a product will cause a work package to exceed its time tolerance

D.

when the team manager identifies that the work package has already exceeded its time tolerance

Questions # 52:

Which is 3 purpose of the ‘plans! practice?

Options:

A.

To enable an event that requires project management consideration to be controlled

B.

To provide the standards against which the project products can be quality controlled

C.

To provide the basis of control against which a project's progress can be monitored

D.

To enable control of opportunities and threats, that could Impact on delivery of the business objectives

Questions # 53:

Identify the missing word(s) in the following sentence.

The 'controlling a stage' process is used to manage and control each [ ? ] of a project.

Options:

A.

delivery step

B.

benefit

C.

delivery stage

D.

team plan

Questions # 54:

Who is responsible for documenting any tailoring of the business case theme?

Options:

A.

Executive

B.

Business project assurance

C.

Project manager

D.

Corporate management

Questions # 55:

Which term is defined-as the amount and type or risk that the business is willing to take in pursuit of is objectives?

Options:

A.

Risk appetite

B.

Opportunity

C.

Risk tolerance

D.

Risk cause

Questions # 56:

Which is a purpose of the 'controlling a stage' process?

Options:

A.

To review the success of the project at the end of a management stage

B.

To agree work package acceptance and delivery requirements

C.

To produce regular highlight reports for the project board

D.

To re-plan the current stage and the project when requested

Questions # 57:

Which is a purpose of the quality theme?

Options:

A.

To establish how the project will ensure that all products created meet their requirements

B.

To establish baselines against which any changes to products can be assessed

C.

To identify all the products of the project to ensure the scope has been adequately defined

D.

To determine the communication needs of the organization’s quality assurance function

Questions # 58:

When is the 'managing a stage boundary' process used?

Options:

A.

Immediately alter the project board has authorized the previous stage

B.

Immediately after the project board has authorized the next stage

C.

Near the end of each stage

D.

Near the end of delivery stages

Questions # 59:

When tailoring PRINCE2 to suit the project, [?] may be changed to suit other standards or policies.

Options:

A.

Defined acceptance criteria

B.

the PRINCE2 principles

C.

the terminology used

D.

the number of themes applied

Questions # 60:

Who are considered as the stakeholders in a project?

Options:

A.

Only those benefitting the project

B.

Everyone in the corporate organization

C.

Everyone involved in or affected by the project

D.

Only those who are users of the products